80   Section Two-FIELD FABRICATION

                HANDLING AND EKECTING HEAVY WALL
                        FABRICATED SPOOL           PIECES


                                   Carbon Steel Material

                                NET MAN HOURS PER FOOT
       Nominal                     WALL THICKNESS  IN INCHES
         Pipe                                                 ,_. —
         Size    .750    1.00    1.25    1.50    1.75    2.00    2.25    2.50
        3 "or less  0.61  0.67           „       ..      „       ..
        4        0.68    0.72    0.84    0.98    ..       „      ..      ....
        5                0.81    0.98    1.14    1.31    1.47    ..      ..
        6         ,.     0.90    1.07    1.22    1.64    1.79    1.95    ..
        8         ..     1.07    1.20    1.43    1.65    1.88    2.10    2.36
        10                ..     1.43    1.50    1.77    2.04    2.31    2.58
        12        „       -      ..      1.76    2.01    2.27    2.54    2.79
        14        ..      ..      ..     2.03    2.25    2.49    2.72    2,96
        16        ..      -      ..              2.42    2.60    2.84    3.11
        18                „              ..      ,-      2.76    2.94    3.23
        20                -              -       „       3.07    3.17    3,33
        22        ..      -      -       -       ..      -       „       3.42
        24        --      --     -       --      --              „      3.50
                 2.75    3.00    3.25    3.50    3.75   4.00     4.25    4.50
        10       2.77    3.14    .,      ,.      ..      ,.      ..      „
        12       3.00    3.39    3.82    4.33                    „
        14       3.16    3.58    4.05    4.58    5,14    5.70
        16       3.33    3.77    4.26    4.80    5.38    5.96    „
        18       3.46    3.91    4.42    5.00    5.59   6.20     „       ..
        20       3.57    4.05    4.58    5.17    5.78   6.43     7.13   7.84
        22       3.67    4.14    4.68    5.29    5.92   6.58     7.29   8.02
        24       3.79    4.28    4.84    5.47   6.12    6.80    7.55    8.29
                 4.75   5.00    5.25    5.50    5.75    6.00
       20        8.01   8.72    9.43    9.82    10.89   11.66
       22        8.20   8.94    9.66    10.43   11.15   11.93
       24        8.48    9.23    9.97   10.78   11.53   12.34
      Man hours are for labor only and include handling and hauling from storage yard, unloading and rigging in place,
      and aligning. This does not include welding, bolt-ups, make-ons or scaffolding. See other pages for these charges.
      Units apply to any length spool piece or segment of work.