                                  Carbon Steel Material
                       DIRECT  MAN HOURS  —  PER  FOOT  BY SIZE

          Pipe                             SCHEDULE  NUMBERS
          Size
         Inches            10 to  60            80  to  100      120 to  160
         1/4                0,26                  0.29             0.30
         3/8                0.27                  0.29             0.32
         1/2                0.27                  0.30             0.34
         3/4                0.28                  0.32             0.35
         1                  0.29                  0.34             0. 39
         1-1/4              0.30                  0.35             0.41
         1-1/2              0.32                  0.37             0.45

         2                  0.34                  0.40             0.49
         2-1/2              0.36                  0.44             0.54
         3                  0.39                  0.48             0.59
         3-1/2              0.40                  0.50             0.62
         4                  0.41                  0.52             0.66
         5                  0.44                  0.57             0.72
         6                  0.47                  0.64             0.84
         8                  0.57                  0.81             0.99

         10                 0.72                  1.00             1.  38
         12                 0.88                  1.23             1.69
         14  OD              1.01                 1.46             2.01
         16  OD              1.27                 1.71             2.34
         18  OD              1.48                 1.96             2.69
         20  OD              1.74                 2.22             3.04
         24  OD              1.94                 2.51             3.43

     Man hours are  for  labor  only and includes  handling and hauling from  storage yard, unloading and
     rigging  in  place,  and  aligning.  It  does  not include  welding, bolt-ups,  make-ons  or scaffolding.
     See other pages  for  these charges.
     For brass, copper  and everdur  pipe, double above  man hours.
     Units  apply  to  any  length spool piece  or  segment  of work.