Page 312 - Facility Piping Systems Handbook for Industrial, Commercial, and Healthcare Facilities
P. 312

SITE UTILITY SYSTEMS

                      6.34                       CHAPTER SIX

                        Depression storage is rain caught in low points on grade and thus not available as runoff.
                        Infiltration is water absorbed into the ground. Investigations have shown that for areas
                        having a CN of 60 to 65, 2 in (50 mm) of rain must fall before runoff even starts. For this
                        reason, a 24-h period is chosen. A heavy concentration of rain falling later in a given storm
                        event will produce a greater peak discharge than at the beginning of the same storm.
                        The 24-h time period is also used to determine total volume of runoff for the same rea-
                      sons. As will be seen, modifications and assumptions must be made to properly estimate
                      runoff from the rainfall amount chosen.
                        The first step in retention basin design is to calculate the peak rate of discharge from
                      the existing site and then from the site as it will be developed. To do this, the CNs of both
                      the original and developed site must be found. When there is only one type of land use
                      and one soil group, this is easy. Otherwise, a weighted CN must be found. This is done by
                      determining the CN for each type of soil condition found and the number of acres for each
                      CN, and multiplying these two figures. The sum of all the products is divided by the total
                      area to find the weighted CN.
                      EXAMPLE  A site consists of 100 acres with two types of land use. One type is 70 acres
                      of pasture land in good condition with soil group C, and the other type is 30 acres of grain
                      field with soil group B. Find the weighted CN for the site.

                      Solution  Refer to Table 6.4 to find the runoff CN. The pasture has a CN of 88, the grain
                      field, a CN of 71.
                                              70 acres ×  88 =  6160
                                              + 30        + 2130
                                                 acres ×  71 =
                                              100         8290
                                            8290
                                                =  82 9 (rounded to 83)
                                                   .
                                            100
                        Therefore, 83 is weighted CN for the entire site.
                        A similar calculation is made to find the CN for the developed site.
                      1.  After the CN has been determined for both the undeveloped site and the developed site,
                        the rate of rainfall and return period should be selected. Local rainfall standards must be
                        used. However, if no standards exist, the maps in Figs. 6.18 (10-year, 24-h rainfall), 6.19
                        (25-year, 24-h rainfall), 6.20 (50-year, 24-h rainfall), and 6.21 (100-year, 24-h rainfall)
                        should be used. Interpolation between isobars is necessary for intermediate values. A
                        recommended average storm would be a 50-year, 24-h rainfall, Fig. 6.20.
                      2.  Next, an adjustment to the 24-h rainfall figure must be made to allow for abstraction and
                        the other considerations that were made when the CN was determined. Table 6.5 reduces
                        the amount of runoff depth according to the various factors previously discussed.
                      3.  Another item required for the determination of peak rate of discharge for the site is the
                        adjustment to rainfall based on the average slope of the watershed. This is the average
                        slope of grade to the storm water inlets, not of the piping system. Figures 6.22 (up to
                        2 percent slope), 6.23 (up to 7 percent slope), and 6.24 (up to 50 percent slope) give the
                        discharge in cfs per inch of adjusted rainfall on the site, according to the average slope
                        for Type II storms. Table 6.6 gives adjustment factors for intermediate slopes other than
                        those found in Figs. 6.22 to 6.24. Type I storm tables are not available.
                        With the CN calculated, it is now possible to calculate the peak rate of discharge for the
                      site. For example, a 300-acre site is to be developed in the northern part of New Jersey. The
                      present weighted CN has been determined to be 75. The average slope of the watershed is
                      found to be 4 percent. A 50-year, 24-h storm has been selected.


                   Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com)
                              Copyright © 2009 The McGraw-Hill Companies. All rights reserved.
                                Any use is subject to the Terms of Use as given at the website.
   307   308   309   310   311   312   313   314   315   316   317