Page 444 - Forensic Structural Engineering Handbook
P. 444

CONCRETE STRUCTURES                  12.35

             • The concrete’s durability was compromised due to extensive cracking and leakage through
              cracks. In the absence of repairs, corrosion of embedded steel reinforcement and related
              concrete deterioration would likely occur relatively early in the service life of the garage.
               The findings indicated that significant repairs were required to ensure structural integrity
                                                                   35
             and provide a durable structure. Four repair alternatives were considered: demolish the
             superstructure and rebuild the garage, using the remaining foundations; remove and replace
             slabs and strengthen deficient beams; install supplemental below-slab framing spanning
             between joists and strengthen deficient beams; and place a bonded reinforced-concrete over-
             lay and strengthen deficient beams.
               Important criteria in evaluating repair alternatives included cost, construction schedule,
             construction methods, the effect of repairs on the remainder of the garage (structural and
             operational), and durability. The bonded reinforced overlay alternative was chosen for sev-
             eral reasons: its estimated cost was lowest of the four options; the repairs could be completed
             in approximately 4 months, with minimal impact on the rest of the garage, because the work
             could be phased; its construction methods were proved, and many contractors have overlay
             experience; and the new overlay slab would provide a durable wearing surface.


             Case Study of Shear Failure in Waffle Slab

             Approximately 8 years after construction was completed, a sudden shear failure occurred at two
             columns around the perimeter of a two-story office building. Figure 12.29 shows the failed slabs
             after curtain walls had been removed. Figure 12.30 shows a close-up of one of the shear fail-
             ures. Temporary timber shoring was placed under the column to provide emergency support.























                FIGURE 12.29  Shear failures of columns on second-story building. (Courtesy of CTLGroup.)

               Once the safety of the building had been secured with emergency shoring, an investigation
             to determine the cause of the failure was begun. Samples of concrete and reinforcement
             were obtained to determine material properties. Simultaneously, plans for the structure
             were obtained and verified by field inspection.
               Figure 12.31 shows framing at each perimeter column for the building. As can be seen,
             columns for the second story did not line up with columns for the first story, but were
   439   440   441   442   443   444   445   446   447   448   449