Page 31 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 31

Project Best Practices    Be st Practice 1.3


                                            Input from project team – propylene refrigeration duty data sheet
                                            Calculations and vendor discussions showed that duty required
                                            a prototype machine in regards to rotor bearing span and shaft
                                            diameter (shaft stiffness)
                                            Risk class was determined as multiple component inexperience
                                            Vendors were invited to pre-screening design review meetings to
                                            determine action
                                            Based on meeting reviews with three vendors, it was determined that
                                            bearing span had to be reduced and that two compressor cases, in
                                            series, were required for proven reliability
                                            Costs of second case were assembled along with supporting data
                                            and cost figures for exposure to reduced availability and
                                            benchmarks of problems experienced with the one case option
                                            (this ‘lesson learned’ information was obtained from experienced
                                            plant maintenance and operations personnel)
                                            The management presentation was successful and additional
                                            $5mm was approved for purchase and installation of the second
                                            compressor casing


                                        Fig 1.2.3   Refrigeration compressor selection case history









               Best Practice 1.3Practice 1.3
               Best
               Screen preferred vendors list by corporate and plant    Excessive time spent in reviewing vendor bids only to disqualify
               experience for the project requirements.              them based on experience
                  Review potential vendors, experience against specific process    A large exception to specifications list resulting in additional review
               conditions for the project to confirm that they have experience for this  time
               project.                                              The potential of accepting an unproven machine for the application,
                  Obtain past project and field experience details for each potential  based on a lower quoted price
               vendor from corporate and plant machinery specialists.    Reduced reliability during operation, resulting in large revenue
                  Do not hesitate to eliminate a potential vendor for this project based  losses.
               on lack of experience.
                  If a vendor is eliminated from quoting, discuss the reasons openly  Benchmarks
               with them, and ensure the vendor that this elimination will not affect  This best practice has been used since the 1970s, and ensures mini-
               future project proposals and is in their interest in terms of proposal cost  mum machinery review time, optimum safety and reliability, and
               savings.                                            maximum revenue over the life of the process. It has been incorporated
                                                                   globally in all upstream and downstream projects. It has resulted in
               Lessons Learned                                     minimum machinery design times, minimum change orders, smooth
               Not screening vendors for experience for the project at  FATs (Factory Acceptance Tests) and trouble free start-ups. These
               hand will result in schedule delays in the selection process  facts have resulted in reduced project costs and schedules and mini-
                                                                   mum start-up times, resulting in early start-ups and increased product
               and lower unit reliability.
                                                                   revenue.
                  Not properly screening vendors for experience for the project
               specific conditions will result in:


              B.P. 1.3. Supporting Material
                                                                      Past project experience –design errors, manufacturing problems,
              Key screening factors for vendor experience for the specific
                                                                      delays, etc.
              project requirements are noted in Figure 1.3.1.
                                                                      Past field experience – availability, maintainability, field support,
                Once these facts are obtained, a list of acceptable vendors  etc.
              for this specific project can be prepared. It is important to note  Vendor's reference lists for the specific project application
              that each specific project will have different requirements and  detailing flow, head, efficiency, etc.
              some vendors will not be in the same position as their com-  Networking with industry peers (API, symposiums, etc.)
              petition in terms of design experience and/or manufacturing
              capability.
                                                                   Fig 1.3.1   Determine potential vendor capabilities
                                                                                                                 5
   26   27   28   29   30   31   32   33   34   35   36