Page 30 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 30

Be st Practice 1 .2           Project Best Practices


         Best Practice 1.2Practice 1.2Practice 1.2
         Best
         Best
         Establish project management team trust, communication    Acceptance of machinery scope by project management without
         and support in the pre-FEED phase of the project.    the knowledge of the machinery project specialist.
           Corporate project culture should require immediate project team    Possible required supplier scope changes during the project
         selection upon project announcement.                 resulting in schedule delays and/or high cost adders.
           Meet with all project team members, and present machinery les-
         sons learned and best practices to project management as soon as the  Benchmarks
         project is announced (pre-FEED phase).             This best practice has been used since the 1970s, and has been in-
           Be sure to include only those best practices that increase safety  corporated into all major projects that the author has been associated
         and show the revenue savings (cost of unavailability) achieved by in-  with in the following industries:
         creased reliability.                                 Upstream oil and gas
           Be sure to benchmark all best practices and cooperate fully with the    LNG
         project team, with timely updates and communication.    Refining
                                                              Chemical
         Lessons Learned                                      Co-generation
         Failure to establish project team support early in the pro-  Good machinery specialist/project management relationships have
         ject will result in lack of implementation of proposed action  resulted in minimum project time for machinery selection, minimum
         and/or possible schedule impact and cost adders.   schedule delays and smooth start-up.
           Not having project management support from the beginning of the  Centrifugal compressor reliabilities have exceeded 99.5% when
         project has resulted in the following issues during the project:  this approach is followed for the entire project (pre-FEED, FEED, test,
           Lack of implementation of company best practices in the project  construction, commissioning and start-up).
           machinery scope.





       B.P. 1.2. Supporting Material
                                                               Present best practices based on lessons learned
       The action taken during the pre-FEED phase (Front End Engi-  Benchmark each best practice in terms of safety and revenue
       neering Design) relative to rotating equipment will set the stage  increase
       for its availability and profit improvement for the entire life of  Present envisioned equipment overview based on input data,
                                                               estimation calculations, prior vendor discussions and best
       the process unit. However, the company must take the initiative  practices
       to assemble and brief the project team members immediately  Define risk – safety and cost of unavailability
       upon project inception. Corporate responsibilities are outlined  Recommend action plan – include: audit, application best
       in Figure 1.2.1.                                        practice and special test requirements
          The corporate action outlined in Figure 1.2.1 will enable the  Define cost and additional schedule time based on
       specialist to acquire the project information that she or he needs  recommended action plan
                                                               Define company savings and increased profit over life of process
       to determine the degree of risk involved for the purchase and
                                                               unit
       manufacture of the critical (custom designed) equipment  Request decision to proceed with the proposed plan
       needed in the project. In addition, the specialist can prepare the
       machinery best practice list from company and plant lessons
       learned, being sure to only select those best practices that affect  Fig 1.2.2   Guidelines for project plan presentation
       safety, and produce significant revenue increases. The manner in  Theformatofthispresentationcanrangefromadiscussionwith
       which project recommendations are presented will have a great  the project engineering manager and project manager to a formal
       impact on project team trust and support. Figure 1.2.2 presents  PowerPoint presentation. Regardless of project team trust and
       these facts.
                                                            type of presentation, time is of the essence and the presentation
                                                            must detail in clear and concise terms, the specific requirements,
                                                            schedule time and life cycle cost savings for the proposed plan.
                                                            An example of turning acquired pre-FEED information into
           Assemble the entire project team immediately upon project  an action plan is presented in the case history in Figure 1.2.3.
           announcement
           The team should include existing plant maintenance, operations  The above action was possible because the project team
           personnel or experienced personnel if the plant is a grass roots  provided early information to the specialists, allowed pre-
           (new) installation                               screening meetings to audit vendor experience and took the
           Brief specialists regarding details of process, size of equipment  specialist’s recommendations seriously.
           special details etc.                               This action took place before the budget estimate. The ex-
           Require specialist input immediately regarding equipment special  ample outlined in Figure 1.2.3 will become more important in
           project requirements (Best Practices)
                                                            the future, as the size of projects increase, and the exposure to
                                                            loss of daily process unit profit can easily exceed millions of
       Fig 1.2.1   Corporate project responsibilities       dollars.

           4
   25   26   27   28   29   30   31   32   33   34   35