Page 590 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 590

The Post-Shipment Phase: Installation, Pre-Commissioning, Commissioning and Start-up Best Practices  Be st Practice 1 0.13


                  The rotor transfers power to the coupling and the    The steam seal limits and directs steam leakage from the
                  load (compressor, generator, etc.)                   shaft to a desired location and not the bearings!
                  The journal bearings support the rotor. A rotor operating at  If the steam seal is worn or the steam seal system is not
                  3600 RPM rotates 60 times per second, 6,000,000 times per day  functioning, water will contaminate the oil and cause premature
                  and 6,000,000,000 times between T&’s, all on less than 0.001”  bearing failure and steel component corrosion
                  oil film! So----

                                                                   Fig 10.12.24   Component Functions cont.
              Fig 10.12.22   Component Functions cont.



                                                                       Since the rotor is much less mass (thinner) than the case,
                  The thrust bearing supports the rotor axially.       it will heat up and cool down at a different rate
                  The condition monitoring of the thrust bearing is most  Therefore, all steam turbines have  required start up
                  important since the rotor will be machined by the nozzles
                                                                       and shut down heating and cooling rates
                  and case if the thrust bearing fails--- and it will be fast!
                  That’s why thrust pad temp. should not exceed 240°F for  Never rapidly start or stop a steam turbine! (Refer to
                  any bearing                                          instruction book)


              Fig 10.12.23   Component Functions cont.             Fig 10.12.25   Start-up and Shut-down











               Best Practice 10.13Practice 10.13
               Best
               Implement the principle of CCM (component condition  reliability. Implementation of a component condition based
               monitoring) for all site machinery to completely monitor all  PDM will optimize machinery safety, reliability and daily
               machinery trains and identify maintenance requirements  revenue for critical equipment.
               for the next turnaround.
                  At the present time (2010), many plants still do not have an effective  Benchmarks
               machinery condition monitoring program, and still rely on either pre-  This best practice has been used since 1990 to achieve optimum
               ventive or breakdown maintenance.                   machinery safety, component MTBFs and reliability in all installations
                  Using the principle of CCM for all site machinery will optimize  that have implemented this best practice.
               machine safety and MTBFs and minimize PM (preventive maintenance)  This best practice is currently being used in the following industries
               and breakdown maintenance.                          to  achieve  optimum  machinery  train  reliability  (compressor
                  Effective communication and integration of maintenance and op-  trains > 99.7%):
               eration personnel will enable many maintenance tasks to be moved to    Oil and gas
               a planned turnaround.                                 Chemical
                  This approach should also be followed for spare equipment, since    Refinery
               maintenance performed on spare equipment during plant operation    LNG
               renders the spared equipment critical (un-spared).
               Lessons Learned
               Absence of an effective site predictive maintenance (PDM)
               program exposes the plant to lower machinery safety and




              B.P. 10.13. Supporting Material

              See B.P: 10.11 for supporting information.





                                                                                                               561
   585   586   587   588   589   590   591   592   593   594   595