Page 137 - Global Project Management Handbook
P. 137

6-6           STATE OF THE ART OF GLOBAL PROJECT MANAGEMENT

        TABLE 6.2  Relative Impact Definitions
        A   Negligible consequence that routine procedure would be sufficient to deal with the
             consequences.
        B   Minor consequence that would threaten an element of the project. Normal control and
             monitoring measures are sufficient.
        C   Moderate consequence would necessitate significant adjustment to the project. Requires
             identification and control of all contributing factors by monitoring conditions and
             reassessment at project milestones.
        D   Significant consequence that would threaten goals and objectives; requires close management.
             Could substantially delay the project schedule or significantly affect technical performance or
             costs, and requires a plan to handle.
        E   Extreme consequence would stop achievement of project or organizational goals and
             objectives. Most likely to occur and prevent achievement of objectives, causing
             unacceptable cost overruns, schedule slippage, or project failure.




           Likelihood of occurrence values also were developed by dividing the probability
        that the identified risk will occur into the following five designations (with numerical
        range from 1 to 5): 1 = very low (<10 percent), 2 = low (10 to less than 35 percent), 3 =
        medium (35 to less than 65 percent), 4 = high (65 to less than 90 percent), and 5 =
        very high (90 percent or greater). These designations are based on the research team’s
        review and assessment of the literature and industry practices for determining and
        assigning risk probabilities. Table 6.3 gives the probability division for the likelihood
        of occurrence used in the IPRA tool.
           As a supplement to the workshops, the October 2002 CII Emerging Markets Forum
        in Baltimore, MD, provided an opportunity for 29 industry representatives to test the
        mechanics of using the IPRA tool and element descriptions on a case study of a
        cement production facility located in Bulgaria. Forum participants were asked to
        assess and comment on the theory, structure, and usefulness of the research team’s
        work. Introducing the IPRA tool to forum participants and having them participate in
        this case-study evaluation proved valuable. The case-study issues and expectations of
        forum participants were well defined during an introduction to the IPRA tool. This
        exploration of the group’s mind-set, combined with a subsequent interactive group dis-

        cussion on assessing the project risks and then reporting the results, helped to (1) create


        TABLE 6.3  Division for Likelihood of Occurrence in the IPRA
        Occurrence                                      Probability
        NA = not applicable to this project.     Zero
        1 = very low chance of occurrence, rare, and occurs only  (<10% chance)
         in exceptional circumstances.
        2 = low chance and unlikely to occur in most circumstances.  (10% chance of occurrence <35%)
        3 = medium chance and possible to occur in most  (35% chance of occurrence <65%)
         circumstances.
        4 = high chance of happening and will probably occur   (65% chance of occurrence <90%)
         in most circumstances.
        5 = very high chance of occurrence and almost   (90% or greater chance of occurrence)
         certain and expected  in most circumstances.
   132   133   134   135   136   137   138   139   140   141   142