Page 139 - Global Project Management Handbook
P. 139

6-8           STATE OF THE ART OF GLOBAL PROJECT MANAGEMENT

        TABLE 6.5  Selected Examples of Unforeseen Project Risk Issues Impacting Performance
        Project       IPRA Risk                     Performance
        ID No.         Element                        Issues

         1       III.A1. Scope development  The initial agreement to stay within scope was not
                      process          followed by the owner, who spent $3 million more
                 III.D8. Schedule      than budget without increasing the project schedule.
                                       The follow-on schedule compression had severe
                                       impacts on the contractor and resulted in increased
                                       labor workloads, costs, and availability on other
                                       projects.
         2       II.A2. VAT            The government sold the project to private investors
                 II.B6. Relationship   and the sale  impacted the contractor’s financing,
                      with government  cash flow, and schedule. To maintain schedule, the
                 III.D8. Schedule      contractor had to use $3 million of its own funds, a
                                       contingency that resulted in VAT and other tax issues.
         5       III. C3. Local design  The requirement to have a local architect and engineer
                       service         approve plans and specifications was not taken into
                 III.D8. Schedule      consideration, and project contingency was used to
                                       pay for the added cost of additional design services
                                       and schedule delays.
         9       II.C3. Religious      The observance of holidays, daily prayer times, and
                      differences      work schedules (local work week was Saturday to
                 III.D8. Schedule      Thursday) decreased productivity. The religious and
                                       cultural differences required the contractor to provide
                                       more on-site management than originally planned.
         9       III.A2. Technology    The use of experimental technology by the process
                 III.D8. Schedule      technology supplier increased plant capacity and
                 III.E2. Facility turnover  process water system specifications for this remote
                                       project. However there were unforeseen problems
                                       with the technology that occurred during start-up and
                                       this adversely affected both cost and schedule. The
                                       contractor’s site staff was required to work with the
                                       client and technology provider to resolve the problems.

         12      II. C1. Traditions and  In-country building practices made it difficult to
                      business practices  achieve plans and specifications. As a result the
                 III.D12. Quality      owner required the construction manager to
                                       increase the number of supervisors to monitor
                                       project performance.




        identify critical risk issues. Members of the research team were involved directly in
        observing the use of the tool on most of these projects. Their observations were
        useful for modifying the assessment sheets slightly and helped them in writing
        instructions on its application for field use.
           The research indicates that many of the highest-impact risks occur in the first two
        sections of the IPRA tool and relate to jurisdictional and financial issues. Organizations
        that have been in a country performing projects appear to have the ability to identify
        and better manage these risks, indicating that the issue of jurisdictional experience is
        important.
   134   135   136   137   138   139   140   141   142   143   144