16 GREEN BUILDINGS TODAY
Figure 2.1 LEED-NC project growth, 2002–2007.
measures. The project serves up to 3000 people per day* and treats, then recycles all
of the building sewage with an onsite treatment plant. Overall, the project expects to
save 60 percent of the energy use of a conventional building and about 56 percent of
the water use. It was built for a reported one percent net cost premium over a con-
ventional building.
TABLE 2.1 LEED-NC CERTIFICATIONS BY ATTAINMENT LEVEL, APRIL 2008*
NUMBER OF CERTIFIED PERCENTAGE OF TOTAL
LEVEL PROJECTS CERTIFICATIONS
Certified 362 36
Silver 331 33
Gold 272 27
Platinum 50 5
Total 1015 100
*U.S. Green Building Council data furnished to the author.