Page 453 - Handbook Of Multiphase Flow Assurance
P. 453
CHAPTER
13
Risk analysis
OUTLINE
Introduction 453 Modeling dynamic behavior 454
Project cost optimization CapEx vs OpEx 453 Integration of various precipitation
phenomena 454
Historic frequency of blockages based on
remediation 453 Impact on overall planning 454
Introduction
Several operator companies are migrating their project development approach from flow
assurance issues prevention to issue risk probability management. This approach allows
to defer cost for the facility development while possibly increasing the operating cost and
difficulty.
Project cost optimization CapEx vs OpEx
Projects tend to be CapEx-lean and OpEx heavy due to the uncertainty in reservoir perfor-
mance. If reservoir is a strong producer and the produced commodity market is expected to
be strong, then additional facilities may be developed.
Historic frequency of blockages based on remediation
The risk-based approach to flow assurance relies on historic frequency of blockages to
forecast the future probability of a blockage.
Historic blockage frequencies and trends were presented in Chapter 5.
Handbook of Multiphase Flow Assurance 453 © 2019 Elsevier Inc. All rights reserved.
https://doi.org/10.1016/B978-0-12-813062-9.00013-0