Page 228 - Handbook of Structural Steel Connection Design and Details
P. 228

Welded Joint Design and Production

                                                   Welded Joint Design and Production  213

                    the minimum requirements of the code may not be adequate under all
                    circumstances. Additional requirements can be communicated
                    through the WPS, such as recommendations imposed by the steel pro-
                    ducer, electrode manufacturer, or others can and should be documented
                    in the WPS.


                    3.5.3 Prequalified welding procedure
                    specifications
                    The AWS D1.1 code provides for the use of prequalified WPSs.
                    Prequalified WPSs are those that the AWS D1 Committee has deter-
                    mined to have a history of acceptable performance, and so does not
                    subject them to the qualification testing imposed on all other welding
                    procedures. The use of prequalified WPSs does not preclude their
                    need to be in a written format. The use of prequalified WPSs still
                    requires that the welders be appropriately qualified. All the work-
                    manship provisions imposed in the fabrication section of the code
                    apply to prequalified WPSs. The only code requirement exempted by
                    prequalification is the nondestructive testing and mechanical testing
                    required for qualification of welding procedures.
                      A host of restrictions and limitations imposed on prequalified weld-
                    ing procedures do not apply to welding procedures that are qualified
                    by test. Prequalfied welding procedures must conform with all the
                    prequalified requirements in the code. Failure to comply with a single
                    prequalified condition eliminates the opportunity for the welding pro-
                    cedure to be prequalified. The use of a prequalified welding procedure
                    does not exempt the engineer from exercising engineering judgment
                    to determine the suitability of the particular procedure for the specific
                    application.
                      In order for a WPS to be prequalified, the following conditions must
                    be met:
                      The welding process must be prequalified. Only SMAW, SAW,
                       GMAW (except GMAW-s), and FCAW may be prequalified.
                      The base metal/filler metal combination must be prequalified.
                      The minimum preheat and interpass temperatures prescribed in
                       D1.1-98 must be employed.
                      Specific requirements for the various weld types must be main-
                       tained. Fillet welds must be in accordance with D1.1-98, Section 3.9,
                       plug and slot welds in accordance with D1.1-98, and groove welds
                       in accordance with D1.1-98, Sections 3.11 and 3.12, as applicable.
                       For the groove welds, whether partial joint penetration or complete
                       joint penetration, the required groove preparation dimensions are
                       shown in the code.




                 Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com)
                             Copyright © 2009 The McGraw-Hill Companies. All rights reserved.
                              Any use is subject to the Terms of Use as given at the website.
   223   224   225   226   227   228   229   230   231   232   233