Page 229 - Handbook of Structural Steel Connection Design and Details
P. 229

Welded Joint Design and Production

                    214   Chapter Three

                      Even if prequalified joint details are employed, the welding proce-
                    dure must be qualified by test if other prequalified conditions are not
                    met. For example, if a prequalified detail is used on an unlisted steel,
                    the welding procedures must be qualified by test.
                      Prequalified status requires conformance to a variety of procedural
                    parameters. These include maximum electrode diameters, maximum
                    welding current, maximum root-pass thickness, maximum fill-pass
                    thickness, maximum single-pass fillet weld sizes, and maximum single-
                    pass weld layers.
                      In addition to all the preceding requirements, welding performed
                    with a prequalified WPS must be in conformance with the other code
                    provisions contained in the fabrication section of AWS D1.1-98
                    Structural Welding Code.
                      The code does not imply that a WPS that is prequalified will auto-
                    matically achieve the quality conditions required by the code. It is the
                    contractor’s responsibility to ensure that the particular parameters
                    selected within the requirements of the prequalified WPS are suitable
                    for the specific application. An extreme example will serve as an illus-
                    tration. Consider the following example of a hypothetical proposed
                                                      3
                                     1
                    WPS for making a  ⁄ 4 -in fillet weld on  ⁄ 8 -in A36 steel in the flat position.
                    The weld type and steel are prequalified. SAW, a prequalified process,
                    is selected. The filler metal selected is F7A2-EM12K, meeting the
                    requirements of D1.1-98. No preheat is specified since it would not be
                                                              3
                                                                                 1
                    required. The electrode diameter selected is  ⁄ 32 in, less than the  ⁄ 4 -in
                    maximum specified. The maximum single-pass fillet weld size in the
                                                                        1
                    flat position, according to D1.1-98 is unlimited, so the  ⁄ 4 -in fillet size
                    can be prequalified. The current level selected for making this particu-
                    lar fillet weld is 800 A, less than the 1000-A maximum specified.
                      However, the amperage level imposed on the electrode diameter for
                    the thickness of steel on which the weld is being made is inappropriate.
                    It would not meet the requirements of the fabrication chapters which
                    require that the size of electrode and amperage be suitable for the
                    thickness of material being welded. This illustration demonstrates the
                    fact that compliance with all prequalified conditions does not guaran-
                    tee that the combination of selected variables will always generate an
                    acceptable weld.
                      Most contractors will determine preliminary values for a prequalified
                    WPS based upon their experience, recommendations from publications
                    such as the AWS Welding Handbooks, from AWS Welding Procedures
                    Specifications (AWS B2.1), or other sources. It is the responsibility of
                    the contractor to verify the suitability of the suggested parameters
                    prior to the application of the actual procedure on a project, although
                    the verification test need not be subject to the full range of procedure
                    qualification tests imposed by the code. Typical tests will be made to




                 Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com)
                             Copyright © 2009 The McGraw-Hill Companies. All rights reserved.
                              Any use is subject to the Terms of Use as given at the website.
   224   225   226   227   228   229   230   231   232   233   234