Page 231 - Handbook of Structural Steel Connection Design and Details
P. 231

Welded Joint Design and Production

                    216   Chapter Three

                    requirement. Secondly, one or more of the specific conditions to be used
                    in the production may deviate from the prequalified requirements. In
                    either case, a test weld must be made prior to the establishment of the
                    final WPS. The first step in qualifying a welding procedure by test is to
                    establish the procedure that is desired to be qualified. The same sources
                    cited for the prequalified WPS starting points could be used for WPSs
                    qualified by test. These will typically be the parameters used for fabri-
                    cation of the test plate, although this is not always the case, as will be
                    discussed later. In the simplest case, the exact conditions that will be
                    encountered in production will be replicated in the procedure qualifica-
                    tion test. This would include the welding process, filler metal, grade of
                    steel, joint details, thickness of material, preheat values, minimum
                    interpass temperature level, and the various welding parameters of
                    amperage, voltage, and travel speed. The initial parameters used to
                    make the procedure qualification test plate beg for a name to define
                    them, although there is no standard industry term. It has been suggested
                    that “TWPS” be used where the “T” could alternatively be used for tem-
                    porary, test, or trial. In any case, it would define the parameters to be
                    used for making the test plate since the validity of the particular para-
                    meters cannot be verified until successfully passing the required test.
                    The parameters for the test weld are recorded on a procedure qualifica-
                    tion record (PQR). The actual values used should be recorded on this
                    document. The target voltage, for example, may be 30 V but, in actual
                    fact, only 29 V were used for making the test plate. The 29 V would be
                    recorded.
                      After the test plate has been welded, it is allowed to cool and the
                    plate is subjected to the visual and nondestructive testing as pre-
                    scribed by the code. The specific tests required are a function of the
                    type of weld being made and the particular welding consumables. The
                    types of qualification tests are described in D1.1-98, paragraph 4.4.
                      In order to be acceptable, the test plates must first pass visual
                    inspection followed by nondestructive testing (NDT). At the contrac-
                    tor’s option, either RT or UT can be used for NDT. The mechanical
                    tests required involve bend tests (for soundness) macroetch tests (for
                    soundness), and reduced section tensile tests (for strength). For quali-
                    fication of procedures on steels with significantly different mechanical
                    properties, a longitudinal bend specimen is possible. All weld metal
                    tensile tests are required for unlisted filler metals. The nature of the
                    bend specimens, whether side, face, or root, is a function of the thick-
                    ness of the steel involved. The number and type of tests required are
                    defined in D1.1-98, Table 4.2, for complete joint penetration groove
                    welds; D1.1-98, Table 4.3, for partial joint penetration groove welds;
                    and D1.1-98, Table 4.4, for fillet welds.
                      Once the number of tests has been determined, the test plate is sec-
                    tioned and the specimens machined for testing. The results of the tests


                 Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com)
                             Copyright © 2009 The McGraw-Hill Companies. All rights reserved.
                              Any use is subject to the Terms of Use as given at the website.
   226   227   228   229   230   231   232   233   234   235   236