Page 245 - Handbook of Structural Steel Connection Design and Details
P. 245

Welded Joint Design and Production

                    230   Chapter Three

                    3.7 Welding Cost Analysis

                    Welding is a labor-intensive technology. Electricity, equipment depre-
                    ciation, electrodes, gases, and fluxes constitute a very small portion of
                    the total welding cost. Therefore, the prime focus of cost control will
                    be on reducing the amount of time required to make a weld.
                      The following example is given to illustrate the relative costs of
                    material and labor, as well as to assess the effects of proper process
                    selection. The example to be considered is the groove weld of beam
                    flange-to-column connections. Since this is a multiple-pass weld, the
                    most appropriate analysis method is to consider the welding cost per
                    weight of weld metal deposited, such as dollars per pound. Other
                    analysis methods include cost per piece, ideal for manufacturers asso-
                    ciated with the production of identical parts on a repetitive basis, and
                    cost per length, appropriate for single-pass welds of substantial
                    length. The two welding processes to be considered are shielded metal
                    arc welding and flux-cored arc welding. Either would generate high-
                    quality welds when properly used.
                      To calculate the cost per weight of weld metal deposited, an equa-
                    tion taking the following format is used:

                                     electrode cost        labor   overhead rate
                    Cost per weight
                                       efficiency    (deposition rate)(operating factor)
                      The cost of the electrode is simply the purchase cost of the welding con-
                    sumable used. Not all of this filler metal is converted directly to deposited
                    weld metal. There are losses associated with slag, spatter, and in the case
                    of SMAW, the stub loss (the end portion of the electrode that is discarded).
                    To account for these differences, an efficiency factor is applied. The follow-
                    ing efficiency factors are typically used for the various welding processes:

                    Process           Efficiency, %
                    SMAW            60
                    FCAW            80
                    GMAW            90 (CO shielding)
                                         2
                                    98 (mixed gas)
                    SAW            100 (flux not included)


                      The cost to deposit the weld metal is determined by dividing the
                    applicable labor and overhead rate by the deposition rate, that is, the
                    amount of weld metal deposited in a theoretical, continuous 1 h of
                    production. This cannot be maintained under actual conditions since
                    welding will be interrupted by many factors, including slag removal,
                    replacement of electrode, repositioning of the work or the welder with
                    respect to the work, etc. To account for this time, an “operating factor”




                 Downloaded from Digital Engineering Library @ McGraw-Hill (www.accessengineeringlibrary.com)
                             Copyright © 2009 The McGraw-Hill Companies. All rights reserved.
                              Any use is subject to the Terms of Use as given at the website.
   240   241   242   243   244   245   246   247   248   249   250