Page 293 - How To Implement Lean Manufacturing
P. 293

270    Cha pte r  S i x tee n


                        •  It took over three weeks to build up enough inventories so we could take the
                           CNC lathe out of service and move it. We did that over one weekend and the
                           lathe started up on Monday without incident.
                        •  The plant ran seven days per week for two more weeks, and then reverted to
                           five days per week operation.
                    The Results
                    Our project had allowed the plant to improve dramatically. Specifically we could now
                    meet demand in a 5 day work week. We were asked to reduce the production lead time
                    by 50 percent and we actually achieved 89 percent reduction using a make–to-stock,
                    pull, production system operating at takt, as requested. We were able to reduce defects
                    by almost 60 percent and improve on-time delivery to over 95 percent, actually achiev-
                    ing 99 percent. In short, by focusing on waste reduction, with an aggressive attack on
                    the seven wastes we met or exceeded all our goals and even achieved two significant
                    gains that were not requested. These included major savings in production labor and
                    space reductions. The labor savings alone showed a 44% reduction in direct labor to
                    produce a motor. All of this was achieved by an aggressive waste reduction effort.
                    Except for the minor cost to produce the universal jigs, no capital was expended. This
                    was a massive success and the results are summarized in Table 16-12.
                    Some comments on the results
                        •  The gains were huge and early, all achieved in less than 2 months.
                        •  Of particular note were the quality improvements. Luis was very worried
                           because we had no specific line items to work on any of the defect modes. As it
                           turned out, by reducing inventory and implementing standard work we accom-
                           plished quality improvements.
                        •  The facility still needed to work on a number of projects. First, and most
                           importantly, although we cut the defects by 60 percent, line rejects are almost
                           6 percent. This is not acceptable by today’s standards, thus they still need to
                           work on this.


                                    Initial Situation    After First Pass of Lean  Improvement
                Production Rate     125 u/day            165 u/day              +32%
                On-time Delivery    76%                  99%                    +23%
                Lead Time           92 hrs (7.5 days)    16 hrs (0.8 days)      –89%
                Line Rejects        14.4%                5.8%                   –59.7%
                Operators per Shift ∗  50                43                     –17.5%
                Labor Consumed      9.33                 5.21                   –44%
                (Mh/motor)

               ∗   In addition to the staffing on the FSVSM, there were three operators in rework, four materials handlers, and
                three in material prep. None of this was changed as yet.
               TABLE 16-12  QED Motors Results Following the Lean Applications
   288   289   290   291   292   293   294   295   296   297   298