 Unit   Date   Solo Runs: Description of Run   Remarks   s+
                                                 os
 CT-0 1   7130198   Turbine solo run: checked mechanical bolt   Vibrations good.   s
 Turbine Solo   trip three times; running approximately six   Outboard bearing thermocouple reading   C&
 hours.                 Hi (215”F), trip set at 4275 rpm, had   s.
                        trouble with vacuum.     3
 CT-0 1   713 1/98   Turbine solo: checked electronic trip   Vibrations good. Outboard bearing   E
 Turbine Solo   three times; running time approximately   TC reading Hi 214”F, trip set at   s
 four hours.            4170 rpm, vacuum problems.
                                                 Sr
 CT-02   8/02/98   Turbine solo: checked bolt trip and   Vibrations good, bearing temps   $
 Turbine Solo   electronic trip each three times; running   good, trip set at 6600
 time approximately six hours.   mechanical bolt trip, 6540
                        electronic trip, had trouble
                        with vacuum. Running time
                        during solo runs for C-01: 10
                        hours, for C-02: 6.0 hours.
 c-01   8/04/98   Air run-in: First air run-in of compressor train:   Vibrations all good-high  temperature
 Train   low pressure-frst  three stages of   turbine outboard bearing, some
 compression; running time approximately   “stall” noticeable on double
 five hours.            flow inboard side at 1500 rpm-
                        none above critical speed, had
                        troubles with condenser,
                        ejectors and seal oil AP.
 Figure 8-10. Event log for charge gas trains.