Page 392 - Improving Machinery Reliability
P. 392

356   Improving Machinery Reliability

                     Work Request  No.                      Date
                     Pump Item No.             Yard No.            Loca t ion
                     Technician  (Name)                   Supervisor
                                                               Telephone Extension

                      How To Use This Checklist:
                       0 During pre-startup operations
                         Place your initials after items you have personally  witnessed to be correct or attach an initialled
                         copy of  the  Machinery Field  Installation  Checklist  to cover items which  Project  Management
                         personnel have reviewed for you.
                       0 When the plant is fully operational
                         Re-install  pumps in accordance with this checklist only. Place your initials after items you have
                         personally  witnessed  to be correct. Do not omit any steps.

                      Mechanical Preparation
                                                                               Initial
                         1.  supry
                            a.  Complied  with  lock-out  and  tag-out procedures  and  wore  proper
                              safety equipment.
                         2.  Prepirittg  pititip urrd basepltrre for  ittstullatiort
                            a.  Cleaned and removed  all burrs from bottom of pump feet and base-
                              plate pads.
                            b.  Cleaned  pump and piping suction and discharge flanges.
                         3. Ptitnp  instullation ott buseplatr
                            a.  Installed pump on base plate and checked the following:
                                I.  Pump feet andlor supporting flanges are square with baseplate
                                  pads and seated solidly.
                                2.  After  tighteniq  the  base  bolts.  the  pump  was  checked for
                                  level and leveled. if necessary.
                                3.  The  pump  was  checked  to  make  sure  that  it  was  slightly
                                  higher than the driver so that shims could be placed under the
                                  driver's  feet during final alignment.
                            b.Horizontal  pumps and drivers rated  100 or more HP have been pro-
                              vided  with  tooling  balls  to facilitate  Essinger  alignment  bar check.
                              Verified  balls to be in  place.
                            c.  IFD isocoupler pads or IFD transducers have been bonded to equip-
                              ment casings as listed below:
                                          driver inboard     17 driver outboard
                                        n pump inboard       5 pump outboard
                                        0 pump central       0 none
                         4.  Piimp rind driwr's couplittR cotic~etrrrit.ity
                            a.  Installed a coupling sweep and dial indicators and checked to make
                              sure that the pump and driver's  coupling halves'  outside diameters
                              and  Paces  were  true  with  their  bores  (maximum  OD  ,002.  face
                          Figure 8-12. Centrifugal pump field installation and initial operation checklist.

                                                                  (checklist continued on next page)