Page 17 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 17

xxxii Introduction


            where F ə ¼allowance multiplier for PF&D, number PF&D¼personal, fatigue,
            and delay allowance, percentage standard productivity—time required by a
            trained and motivated worker or workers to perform construction task while
            working at normal tempo.

                                       H s ¼ T n  F ə
            where H s ¼standard time for a construction task per unit of effort, hour. The
            allowance for PF&D is 15%, which is an allowance multiplier of 1.176.
               Definitions for nonrepetitive one-cycle time study are given in Table 2.



              TABLE 2 Definitions for productivity analysis
              Task/operation  Designated and described work sublet to work measurement,
                            estimating, and reporting.
              Normal time   An element or operation time found by multiplying the average time
                            observed for one or multiple cycles by a rating factor.
              Element       A subpart of an operation or task separated for timing and analysis;
                            beginning and ending points are described, and the element is the
                            smallest part of an operation observed by time study. The length of the
                            element can vary from minutes, to hours, to days, etc.
              Rating factor  A means of comparing the performance of the worker under
                            observation by using experience or other benchmarks; additionally, a
                            numerical factor is noted for the elements or cycle; 100% is normal,
                            and rating factors less than or greater than normal indicate slower or
                            faster performance.
              Observed time  The time observed on the stopwatch/electronic clock or other media
                            and recorded on the time study sheet or media tape during the
                            measurement process.
              Cycle         The total time of elements from start to finish.
              Continuous    A method of time study where the total elapsed time from the start is
              time          recorded at the of each element.
              Standard time  Sums of rated elements that have been increased for allowances.
              Allowance     An adjustment for work, which includes delays, idle time, and
                            inefficiency, as well as efficient effort.
              Delay         One part of the allowance included in the standard time for
              allowance     interruptions or delays beyond which the worker’s ability to prevent.
              Fatigue       An allowance based on physiological reduction in ability to do work,
              allowance     sometimes included in the standard time.
              Idle time     An interval in which the worker, equipment, or both are not
                            performing useful work.
              Person/man-   A unit of measure representing one person working for one hour.
              hour
   12   13   14   15   16   17   18   19   20   21   22