Page 279 - Intro Predictive Maintenance
P. 279

270       An Introduction to Predictive Maintenance

         affected by system variations, no matter how simple or complex. For example, a com-
         parison of vibration profiles acquired from a centrifugal compressor operating at 100
         percent load and at 50 percent load will clearly be different. The amplitude of all rota-
         tional frequency components will increase by as much as four times at 50 percent
         load. Why? Simply because more freedom of movement occurs at the lower load.
         As part of the compressor design, load was used to stabilize the rotor. The designer
         balanced the centrifugal and centripetal forces within the compressor based on the
         design load (100 percent). When the compressor is operated at reduced or excessive
         loads, the rotor becomes unbalanced because the internal forces are no longer equal.
         In addition, the spring constant of the rotor-bearing support structure also changes
         with load: It becomes weaker as load is reduced and stronger as it is increased.

         In more complex systems, such as paper mills other continuous process lines, the
         impact of the production process is much more severe. The variation in incoming
         product, line speeds, tensions, and a variety of other variables directly impacts the
         operating dynamics of the system and all of its components. The vibration profiles
         generated by these system components also vary with the change in the production
         variables. The vibration analyst must adjust for these changes before the technology
         can be truly beneficial as either a maintenance scheduling or plant improvement tool.

         Because most predictive maintenance programs are established as maintenance tools,
         they ignore the impact of operating procedures and practices on the dynamics of
         system components. Variables such as ramp rate, startup and shutdown practices, and
         an infinite variety of other operator-controlled variables have a direct impact on both
         reliability and the vibration profiles generated by system components. It is difficult,
         if not impossible, to accurately detect, isolate, and identify incipient problems without
         clearly understanding these influences. The predictive maintenance program should
         evaluate existing operating practices; quantify their impact on equipment reliability,
         effectiveness, and costs; and provide recommended modifications to these practices
         that will improve overall performance of the production system.


         13.1.4 Training Limitations
         In general, predictive maintenance analysts receive between 5 and 25 days of train-
         ing as part of the initial startup cost. This training is limited to three to five days of
         predictive system training by the system vendor and about five days of vibration or
         infrared technology training. In too many cases, little additional training is provided.
         Analysts are expected to teach themselves or network with other analysts to master
         their trade. This level of training is not enough to gain even minimal benefits from
         predictive maintenance.

         Vendor training is usually limited to use of the system and provides little, if any, prac-
         tical technology training. The technology courses that are currently available are of
         limited value. Most are limited to common failure modes and do not include any train-
         ing in machine design or machine dynamics. Instead, analysts are taught to identify
         simple failure modes of generic machine-trains.
   274   275   276   277   278   279   280   281   282   283   284