Page 413 - Intro Predictive Maintenance
P. 413

404       An Introduction to Predictive Maintenance

         Table 18–1 Twelve-Point Data Collection Process Facilitates Analysis of OEE Information

                              Overall Equipment Effectiveness
          1. Planned Time Available                             7,200 minutes
            8 hours ¥ 60 minutes = 480 minutes ¥ 15 turns or shifts
          2. Planned Downtime                                    250 minutes
            For preventive maintenance, lunch, breaks, etc.
          3. Net Available Run Time                             6,950 minutes
            Item 1 - Item 2
          4. Downtime Losses                                    4,640 minutes
            Breakdowns, setups, adjustments
          5. Actual Operating Time                              2,310 minutes
            Item 3 - Item 4
          6. Equipment Availability                             33%
            Item 5
                 ¥100
            Item 3
          7. Total Output for Operating Time                    15,906 units
            Total produced in units, pieces, tons, etc.
          8. Design Cycle Time                                  0.109 minutes/unit
          9. Operational Efficiency                              75%
            Item 8 ¥  Item 7
                        ¥100
               Item 5
         10. Rejects During Turn (Shift)                        558 units
         11. Rate of Product Quality                            96.8%
            Item 7 Item 10
                 -
                         ¥100
                Item 7
         12. OEE                                                23.96%
            Item 6 ¥ Item 9 ¥ Item 11

         equipment effectiveness in most U.S. companies barely breaks 50 percent. It is little
         wonder that there is so much room for improvement in typical equipment maintenance
         management programs.

         A plastic injection molding plant had a press with the following statistics:

               • The press was scheduled to operate 15 eight-hour shifts per week.
               • This gave a total possibility of 7,200 minutes of run time per week.
               • Planned downtime for breaks, lunches, and meetings totaled 250 minutes.
               • The press was down for 500 minutes for maintenance for the week.
               • The changeover time was 4,140 minutes for the week.
               • The total output was 15,906 pieces.
               • The design cycle time was 9.2 pieces per minute.
               • There were 558 rejected pieces for the week.
               • What is the OEE for the press for the week in question?

         A form to collect and analyze OEE information is pictured in  Table 18–2. The
         equipment availability is calculated in the first section of the form. The gross time
   408   409   410   411   412   413   414   415   416   417   418