Page 414 - Intro Predictive Maintenance
P. 414

World-Class Maintenance     405

            Table 18–2 Overlaying World-Class Standard on the Baseline Data

                                 Overall Equipment Effectiveness
             1. Planned Time Available                             7,200 minutes
               8 hours ¥ 60 minutes = 480 minutes ¥ 15 turns or shifts
             2. Planned Downtime                                   250 minutes
               For preventive maintenance, lunch, breaks, etc.
             3. Net Available Run Time                             6,950 minutes
               Item 1 - Item 2
             4. Downtime Losses                                    695 minutes
               Breakdowns, setups, adjustments
             5. Actual Operating Time                              6,255 minutes
               Item 3 - Item 4
             6. Equipment Availability                             90%
               Item 5
                    ¥100
               Item 3
             7. Total Output for Operating Time                    54,516 units
               Total produced in units, pieces, tons, etc.
             8. Design Cycle Time                                  0.109 minutes/unit
             9. Operational Efficiency                              95%
               Item 8 ¥  Item 7
                           ¥100
                  Item 5
            10. Rejects During Turn (Shift)                        545 units
            11. Rate of Product Quality                            99%
               Item 7 Item 10
                    -
                            ¥100
                   Item 7
            12. OEE                                                85%
               Item 6 ¥ Item 9 ¥ Item 11



            available for the press is entered in line 1. The planned downtime, which involves
            activities that management sets a priority on and cannot be eliminated, is entered in
            line 2 (the 250 minutes for the week). The net available time for operation is entered
            in line 3 (this is actually line 1 minus line 2).  The downtime losses, which are
            all unplanned delays, are entered in line 4.  This would include maintenance
            delays, changeovers (which can be minimized), setups, adjustments, and so on. The
            actual time the press operated is entered on line 5 (this is the difference between lines
            3 and 4). The equipment availability (line 6) is line 5 divided by line 3 times 100
            percent.

            The OEE is calculated in the next section. The total output for the operating time is
            entered in line 7. The actual design cycle time (this number must be accurate) is entered
            on line 8. The operational efficiency is calculated and entered on line 9. The opera-
            tional efficiency is line 7 (the total output) times line 8 (design cycle time) divided by
            line 5 (the actual operating time) times 100 percent. This number should be evaluated
            carefully to ensure that the correct design capacity was used. If the percentage is high
            or exceeds 100 percent, then the wrong design capacity was probably used.
   409   410   411   412   413   414   415   416   417   418   419