Page 77 - Lean six sigma demystified
P. 77

56        Lean Six Sigma  DemystifieD












                                            8 hrs  Sales  8 hrs
                                                   Order        Scheduler
                            Customer   Sales rep
                                             Kanban
                          CT = Cycle Time
                          CO = Change Over
                          UT = Up Time
                           1  = Inventory  Supermarket
                                                  Kaizen
                            Process 1  100    Process 2          Process 3          Process 4
                            CT = 15 sec       CT = 15 sec  100   CT = 15 sec  100  CT = 15 sec
                            Crew = 1   units   Crew = 1  units    Crew = 1  units   Crew = 1
                            CO = 10 min       CO = 10 min        CO = 10 min       CO = 10 min
                           Uptime = 100%     Uptime = 100%      Uptime = 100%     Uptime = 100%
                            Waste = 5%        Waste = 5%         Waste = 5%        Waste = 5%
                           Avaliable sec =   Avaliable sec =    Avaliable sec =   Avaliable sec =
                             27600    1 day    27600     1 day    27600    1 day     27600
                                      1 day              1 day              1 day
                             15 sec            15 sec             15 sec            15 sec
                                                                                      1    100
                                                                                      D    units
                                                                                      a
                                                                                      y









                     FIGURE 2-5 • QI Macros value stream map.




                          •   Requests for change may spend months in a prioritization cue before
                             being worked (non-value-added.)

                          •   An order may sit idle waiting for an approval or material.
                          On a process flowchart or value stream map, most of the non-value-added
                        time will be found in one of three places.

                          •   Arrows. Delay between process steps

                          •   Rework loops. Fixing errors that should have been prevented
                          •   Scrap processes. Discarding or recycling defective products