Page 108 - Machinery Component Maintenance
P. 108
Machinery Foundations and Grouting 91
and at least two ft into the undamaged concrete below. In addition, holes
can be drilled in the remaining part of the foundation shoulders at such
angles so as to cross below the oil pan at an elevation of approximately
two to three ft below the pan or trough. Afterward, additional horizontal
reinforcing steel can be installed and wired to the vertical members
which were earlier cemented into the good concrete with an epoxy adhe-
sive. The purpose of the new reinforcing steel is to transfer as much load
as possible to an area where the concrete was unaffected by oil dcgrada-
tion.
Pressure-Injection Regrouting
Pressure-grouting is a repair process whereby equipment can be reaf-
fixed on the foundation without lifting the equipment, without completely
chipping away the old grout, and without repositioning and complete re-
grouting. Pressure grouting should not, however, be considered a pana-
cea. Nevertheless, when properly used it can be a valuable tool.
Shoulder Removal Method
Pressure-injection regrouting techniques offer equipment operators im-
portant advantages of reduced downtime, lower labor costs, and less rev-
enue lost from idle equipment. These techniques make possible satisfac-
tory and long life regrouts with machine downtime at a minimum.
Figure 3-9 shows typical damage before making repairs. Figure 3-10 is
the first step in conducting repairs where the old grout is chipped away
Figure 3-9. Illustrating the damage done to a compressor foundation before making re-
pairs by pressure-injection regrouting, shoulder removal method (Courtesy Adhesive Ser-
vices Company).