Maintenance Organization and  Control for Multi-Plant Corporations   45

                        Thc mechanical  supervisors instruct the spare parts  coordinator  to
                        assemble up-to-date tabulation of spare parts presently on hand  for
                        major machinery trains. After review, they forward the tabulation to
                        the senior machinery  specialist.

                    Eight Months Before T/A:
                        The spare parts coordinator and maintenance personnel  receive the
                        senior machinery  specialist’s request to:
                        I.  Place a “hold” on selected parts
                        2.  Order additional spare parts
                        In response,  they issue purchase  orders for additional  replacement
                        parts.
                        Next, maintenance supervisors commence dimensional checking of
                        selected (existing) spare parts per  request  made by  the  senior  ma-
                        chinery  specialist.  The results  should be documented  within  eight
                        days.
                        Dimensional checking has frequently shown serious discrepancies in
                        parts designation, dimensional configurations, and tolerances. These
                        must be identified early if a smooth turnaround is to result.
                    Six Months Before T/A:
                        Maintenance personnel arrange for vendor assistance.
                        Maintenance personnel also work up a more definitive work zone ar-
                        rangement and commence tabulation of detailed  work  list for each
                        zone.
                        Maintenance or technical department  personnel  witness check bal-
                        ancing of major turbomachinery rotors.
                        Assemble tools and identify missing tools.
                        Arrange for scaffolding, etc.
                        Forward data to senior machinery specialist regarding status of spare
                        parts ordered six months earlier.
                        The planner  should now provide  final work zone arrangement  and
                        detailed work list for each.

                    One month before T/A, maintenance planners or mechanical supervisors
                    provide bar chart diagrams for machinery-related  T/A work.
                        They participate in a meeting with the  senior machinery  specialist
                        and designated turbotrain T/A engineers.

                      One  week  before  T/A,  mechanical  supervisors  commence  meeting
                    with designated turbotrain  T/A engineers for briefings on matters relat-
                    ing to machinery  work.