Page 594 - Marine Structural Design
P. 594

570                                                      Part V Risk Assessment

                 The  development  phase  starts  with  the  conceptual  engineering, which  is  based  on  the
                 recommendations of the PDO. The final field development concept is then fixed, along with
                 the operation philosophy, safety, and environmental programs, etc. Subsequently, the whole
                 project is executed systematically: engineering, procurement, construction, and  installation.
                 Meanwhile, production wells are being drilled if pre-drilling is recommended.
                 The operation phase typically has a period of 20 years. The production will initially increase
                 and reach its maximum, and then it gradually declines. Meanwhile, reservoir engineering will
                 continue  to  maximize  the  production,  based  on  updated  reservoir  information.  The
                 decommission phase is at the end of the field life. The platform is abandoned and removed
                 from the site.
                 32.1.2  Background of Economic Evaluation

                 Economic evaluation is carried out throughout the life cycle of a field development project.
                 Net Present Value (NPV) and Internal Rate of Return (IRR) are the two most basic decision
                 criteria. Recently, Life-Cycle Cost (LCC) criterion is frequently used in decision-making, and
                 it is actually derived based on NPV.
                 Before and during the exploration, economic evaluation is mainly applied to assess whether or
                 not the required investment in this project is profitable enough. An exploration decision is like
                 a major gamble: a large field may be discovered, or at the other extreme, no oil or gas found at
                 all. However, the costs incurred in individual explorations are relatively low compared to the
                 total cost of field development if the  exploration is successful. The economic evaluation is
                 repeated at  each  stage  during the  exploration, and  the  results  could  culminate in  a  final
                 decision to invest in developing the discovery. Classic economic evaluation methods by using
                 Net Present Value (NPV) or Internal Rate of Return (IRR) are preferred in this phase. The
                 definitions of NPV and IRR are provided in Appendix I.
                 Once the project is approved and is ahead in the development and operation phases, the Life
                 Cycle Cost (LCC) approach is preferable. In the LCC model, all of the relevant economic
                 implications of a decision and the effects on the operating company may be considered. For
                 example, by using the LCC model, the total cost of a production facility could be expressed by
                 the sum of the following cost elements (NORSOK 0-CR-0002):
                    Capital costs (CAPEX)
                    Operating cost (OPEX), which covers operation and maintenance
                    Cost of deferred production
                 The initial capital expenditure of the facility is then not the only criterion for decision-making.
                 Instead, the optimum design concept is chosen as the one that provides the minimum life cycle
                 cost.
                 32.1.3  Quantitative Economic Risk Assessment
                 The economic risks  involved in the  field development projects vary,  and may include (1)
                 technical risks  (which may  ultimately have  their  economic  impact),  (2) commercial risks
                 (associated mainly with cost and income variables), (3) potential natural disaster, and so  on.
                 Uncertainties may include: (1) reservoir information such as production profiles, recoverable
                 oil and gas, (2) cost parameters such as cost of fabrication, transportation, installation, and cost
                 of  operation, maintenance, (3)  financial variables  such  as interest  rate,  oil  price,  etc.  A
                 systematic economic risk  assessment is therefore needed  to  assess the impact of risks and
   589   590   591   592   593   594   595   596   597   598   599