               The  objective  of  the  present  research  is  to  develop  an  integrated  process  planning  and  scheduling  system
               applicable to the holonic manufacturing  system. In the previous papers (3H<5) , integration of process planning  and
               scheduling was  carried  out, wherein  the  scheduling  system  for  multi-products  as a whole uses the process  plan
               information  of  a  set  of  individual  products  to  generate  a  suitable  schedule.  But,  there  is  not  any  feedback
               information  from  the scheduling  system to the process planning system. This paper deals with the integration of
               the process planning  and the  scheduling  systems where there  is a  scheduler  driven  modification  of the  process
               plans of the products. A systematic method  is proposed to generate modified  sequences of machining  equipment
               for the individual products based on the feedback information of the scheduling results, and to generate a modified
               production schedule for the whole manufacturing  system.



               PROCESS PLANNING AND SCHEDULING



               The process planning system generates suitable process plans for the individual products to be manufactured.  The
               process plans give suitable sequences of manufacturing  equipment needed to manufacture the machining  features
               of  the  products,  and  machining  time  of  the  machining  features.  The  scheduling  system  determines  suitable
               production  schedules  of  manufacturing  equipment  in  the  HMS  for  manufacturing  a  set  of  products.  The
               production schedules give the loading sequences of the products to the manufacturing  equipment and the  starting
               times of the individual machining processes of the products. The production  schedules are verified  based on the
               objective functions  such as the make span and the tardiness against due date.


               SCHEDULING BY SCHEDULING HOLON



               Input  Information
               The  input  information  of  the  scheduling  holon  is  summarized  here.  The  following  production  management
               information  is the requimements to the scheduling process.
               (1) Starting time and due time of job holons.
               (2) Candidate machining sequence of machining features and candidate sequences of machining equipment.
               (3) Machining time of machining features.
               (4) Alternative machining equipment for each machining feature.
               (5) Machining time by alternative machining equipment.

               Objective  Functions

               This research deals concurrently with both the process planning of the individual jobs and the scheduling of all the
               jobs to be manufactured  in the HMS. The following  objective functions  are considered for the scheduling task of
                     (5)
               theHMS .
               (1) Make span: MS
               (2) Total machining cost: TMC
               (3) Weighted tardiness cost: WT