Page 363 - Offshore Electrical Engineering Manual
P. 363

350    CHAPTER 2  Generators




                             temporary means of preventing rotation. The start permissive key should be
                             removed from the prime mover control panel. Having made certain that every-
                             thing is electrically and mechanically safe, work can then begin on testing the
                             generator windings.
                           3.   Cold resistance of main stator windings
                               The method involves injecting a known direct current through each winding
                             and measuring the voltage drop through the winding at the terminals. Before
                             applying the current, the earth must be removed from the winding. Readings
                             of voltage and current should be recorded for all three phases. The three
                             resistances calculated from these readings after compensating for ambient
                             temperature should not deviate from each other by more than 2% or from the
                             manufacturer’s design figure by more than 5%. For compensation purposes,
                             the ambient air temperature will need to be measured at shaft height and 1 m
                             from the alternator frame.
                           4.   Rotor and exciter field windings
                               The resistance of these windings should be measured in the same way as the
                             stator windings. Using an alternating current high-voltage test unit, the genera-
                             tor windings should be tested to twice their working voltage plus 1000 V, with
                             a minimum of 1500 V as required in BS 4999. The windings should withstand
                             this voltage for 1 min. The voltage should be gradually applied, and the minute
                             count started once full test voltage has been reached.
                           5.   Exciter
                               The exciter field should be tested in the same way and using the same criteria
                             after temporarily removing the AVR connections. With a brushless machine,
                             the rotor and exciter armature should be checked for continuity only, in order
                             to avoid damage to the diode bridge.
                           6.   Anticondensation heaters
                               Anticondensation heaters should be high voltage tested to about 1500 V to the
                             machine frame, with adjacent windings earthed. A continuity check should
                             also be carried out.
                           7.   Insulation resistance
                               Using a ‘Megger’ of suitable voltage rating (5000 V for medium-voltage and
                             1000 V for low-voltage machines), the insulation resistance should be mea-
                             sured. Minimum values acceptable are as follows:

                                            Stators           50 MΩ
                                            Exciter field     10 MΩ
                                            Exciter armature  10 MΩ
                                            Rotor             10 MΩ

                                    Note that during any of the high-voltage or Megger tests, all voltage-
                             sensitive auxiliaries, thermistors, auxiliary windings, etc. should be  temporarily
                             earthed to avoid damaging them. No part of the AVR or rotating diode bridge
                             should be meggered, if damage is to be avoided.
   358   359   360   361   362   363   364   365   366   367   368