Page 118 - Orlicky's Material Requirements Planning
P. 118

CHAPTER 6      The Material Requirements Planning System                         97


             In an MRP system, the net-requirement quantities are always related to time, that is,
        to some date or period. The net requirements then are covered by planned orders, and
        the order quantities either match net requirements or are calculated by employing one of
        several lot-sizing techniques designed to take into account the economics of ordering.
        The timing of planned-order releases is also determined by the MRP system, and the
        information is stored for purposes of future order action.
             The function of providing coverage of net requirements is served only in part
        through planned (i.e., future) orders. The MRP system also reevaluates the timing of open
        orders relative to (possibly changed) net requirements in the near future, and it signals
        the need for rescheduling these orders, forward or backward in time, as required, to
        realign coverage with net requirements.


        THE PURPOSE OF THE SYSTEM
        An MRP system is capacity-insensitive in that it will call for the production of items for
        which capacity may not, in fact, exist. This might appear to be a shortcoming of MRP, but
        on a moment’s reflection, it can be seen that this is not so. A system can be designed to
        answer either the question of what can be pro duced with a given capacity [i.e., what the
        master production schedule (MPS) should be] or the question of what need be produced
        (i.e., what capacity is required) to meet a given MPS, but not both simultaneously. Process
        industries tend to ask the capacity question first, whereas discrete manufacturing com-
        panies tend to ask the latter question first. Current MRP systems are designed to answer
        the both questions iteratively. The industry will determine which question is asked and
        answered first. See Chapters 15 through 18 for more detail by industry.
             An effective MRP implementation assumes that capacity considerations have
        entered into the makeup of the MPS. An MRP system “believes” the MPS, and the valid-
        ity of its outputs is always relative to the contents of that schedule. Another way of stat-
        ing this is to say that the MPS can be invalid (vis-à-vis available capacity), but the out-
        puts of an MRP system (assuming valid file data and correct proce dures) cannot.
             The output of an MRP system is not necessarily always realistic in terms of lead
        time, capacity, and availability of materials, particularly when the system plans require-
        ments for an unrealistic MPS. It is then merely saying, “This is what you would have to
        be able to do to implement the schedule.” Why the schedule is unrealistic thus is re vealed
        in specific terms.
             In any manufacturing operation, the questions of what materials and com ponents
        are needed, in what quantities, and when—and the answers to these questions—are vital.
        An MRP system is designed to provide just these answers. MRP systems are a highly
        effective tool of manufacturing inventory man agement for the following reasons:

             ■ Inventory investment can be held to a minimum.
             ■ An MRP system is change-sensitive and reactive.
             ■ The system provides a look into the future on an item-by-item basis.
   113   114   115   116   117   118   119   120   121   122   123