Page 140 - Orlicky's Material Requirements Planning
P. 140

CHAPTER 7   Processing Logic                                                    119


        its due date to arrive at the order release date. The actual span of time might be more than
        five weeks if holidays or a plant vacation hap pened to intervene.


                                 Dates and Time Buckets

        In an MRP system, inventory status data are time  phased by associating them with either
        days (relatively short time periods) or planning periods such as weeks or months (rela-
        tively long time periods). While the specific method of time phasing that is being
        employed will de termine the terms in which the internal arithmetic is carried out by the
        system, the method of display of time-phased data can be selected independently. A given
        day can be converted to its respective planning period for purposes of display, and a plan-
        ning period can be expressed in terms of one of its constituent days, usually its starting
        day. Figure 7-1 demonstrates how these data can be displayed by different time buckets.

           FIGURE 7-1
                                                               Period
           Row of different
                                           1  2    23 24 25 26 Jul AugSepOct NovDec  I  II  III IV
           time values
           display.            Gross
                               Requirements  10 15  5  20 10 10 40 305050 50 30  120150150 100

             MRP systems are designed in such a way that requirements and inventory data can
        be entered, stored, and processed internally by date/quantity but displayed in time-
        bucket format. Technological developments over the past 30 years have allowed MRP
        systems to develop into ”bucketless” systems. The development of time buckets that cor-
        respond to periods of time normally spanning more than a single day is no longer
        required. This represents a rather coarse division of time. For this reason, the precise
        meaning of the timing of data assigned to time  buckets was fixed by convention.
        Currently, MRP systems schedule to the day. Therefore, the logic of time buckets is no
        longer necessary. In the following discussion of gross and net requirements, although
        time periods can be a day, a week, a month, or a quarter, the common deployment in
        MRP is that a period is a single day.


                                      Planning Horizon
        To ensure that MRP provides data on items at all levels in bills of material (BOMs), the
        planning horizon at least should equal the largest total of item lead times (cumulative
        lead time) in the critical (longest) path leading from raw material to the end item appear-
        ing in the master production schedule (MPS). If planning horizons are too short, the
        process of successively offsetting for lead time in level-by-level planning will run into
        past periods when it reaches items on the lowest level. To ensure some forward visibility
        of data on purchased items, planning horizons should be significantly longer than the
        critical-path lead time.
   135   136   137   138   139   140   141   142   143   144   145