Page 223 - Orlicky's Material Requirements Planning
P. 223

202                                                 PART 3      Managing with the MRP System


           FIGURE 11-2
                                                            Period
           Transient
           subassembly B,                                  1   2
           its parent, and
           component.
                                       Schedule Receipts
                               Part A  On Hand

                                       Planned-Order Releases  20




                                       Gross Requirements  20
                                       Allocated

                               Part B  Schedule Receipts
                                       On Hand          2  –18 –18
                                       Planned-Order Releases  18





                                       Gross Requirements  18
                                       Allocated
                               Part C
                                       Schedule Receipts
                                       On Hand         30  12  12



             Following release of the planned order for A, the update procedure for item record
        B will vary depending on whether or not it is coded as a phantom. In the absence of such
        a code, regular logic applies. The regularly updated records of items A and B are shown
        in Figure 11-3.
             Record C continues unchanged. Following release of the planned order for B, item
        record C is updated, as shown in Figure 11-4.
             Had item B been coded as a phantom, all three records would have been updated in
        one step, as illustrated in Figure 11-5, as a result of the planned-order release of item A.
        Note that the release of planned order A, which normally would reduce only the corre-
        sponding gross requirement  B (as in Figure 11-3), in this case also reduces the gross
        requirement for C as though C were a direct component of A.
             Note also that the two units of B in stock (perhaps a return from a previous overrun)
        are applied to the gross requirements for A and that the allocation has been distributed
        between B and C. On closer examination of these examples, it can be seen that the phan-
        tom logic is nothing more than a different treatment of allocation. (Zero-lead-time and
   218   219   220   221   222   223   224   225   226   227   228