Page 244 - Orlicky's Material Requirements Planning
P. 244

CHAPTER 12   Master Production Schedule                                         223


           FIGURE 12-1

           A master production schedule (MPS).
                                                   Planning Horizon

                                        Firm                     Tentative

                          Month  A  M  J   J  A   S  O   N   D   J  F   M  A   M   J
                   Product
                   Hoist #35    50         50        50         60         60
                   Hoist #45       100     80     75     60            50
                   Hoist #55   200 200 200 150 150 100 100 100  150 150  200 250 250 250 250






                      Week
              End Item     16  17  18  19
              Motor 3848   60     60
              Motor 4002   30  30  30  30
              Drum 12-305  25  50



        issues of an updated version of the MPS, however, there may arise a need for revision at
        any time, as a result of the particular mix of new customer orders and the various
        unplanned developments in procurement and manufacturing. It is highly desirable,
        therefore, for the MRP system to be able to process intervening and intermittent “unoffi-
        cial” changes in the MPS on a more frequent basis than that afforded by the forecasting
        cycle. As discussed in Chapter 14, an MRP system loses much of its effectiveness if it is
        not used to replan daily. Arguments for continuous replanning of material requirements
        were presented in Chapter 7.


        THE FINAL ASSEMBLY SCHEDULE
        In order to comprehend the essence and the true function of the MPS, a distinction must
        be drawn between it and the final assembly schedule. This was touched on earlier in con-
        nection with other topics, but at this point, a more thorough discussion is warranted. The
        distinction between these two schedules is a source of frequent confusion because in
        some cases the schedules, although always different in concept, may be identical in real-
        ity; that is, the final assembly schedule may serve as the MPS.
             There may be no difference between these two schedules where the product line is
        limited or where the product itself is small and/or simple. Lawnmowers, hand tools,
   239   240   241   242   243   244   245   246   247   248   249