Page 249 - Orlicky's Material Requirements Planning
P. 249

228                                                 PART 3      Managing with the MRP System


             ■ A part of the demand expressed in the schedule of factory requirements may be
                met from plant inventory.
             ■ Product lot-sizing considerations, important from the manufacturing point of
                view, are obviously not reflected in the schedule of factory requirements. The
                demand is shown by quantity and date without regard for production econom-
                ics. In the process of developing the MPS, product lot sizes are established that
                may deviate in both quantity and timing from the requirements of the various
                sources of demand. Additional lot sizing may take place subsequently at the
                component-item level.

             The load represented by the schedule of factory requirements either may exceed
        productive capacity or be below the capacity to which the plant is committed. This load
        may fluctuate excessively. The schedule of factory requirements may be stated in terms
        of product models that will have to be translated into end-item BOM numbers. The
        schedule of factory requirements may not specify optional product features the demand
        for which must be forecast before being incorporated into the MPS.
             The schedule of factory requirements serves as the basis for final preparation of the
        MPS, which constitutes the third and final step in MPS development. Thus a specific
        manufacturing program is created that will then be processed by the MRP system to plan
        all subsequent component procurement, fabrication, and subassembly activity. In trans-
        forming the schedule of factory requirements into an MPS, the predominant considera-
        tion is that of capacity availability. The process and techniques used to achieve a balance
        between load and capacity over the long horizon are described next.


                           Resource Requirements Planning
        An MPS must be considered in relation to the load it places on available or planned
        resources, including capacity, space, and working capital. If available resources are not
        adequate to meet the requirements represented by a given MPS, they must be increased,
        or the schedule should be reduced. Unless solid planning of resource requirements takes
        place before the planning of production, there is a likelihood of failure in delivery service,
        a logjam in work-in-process, a disruption in the production control system, and increased
        manufacturing costs.
             The resource requirements planning concept entails a long-range planning function
        intended to keep in balance the ability to meet demand and a reasonably level load on
        the company’s resources. The technique of resource requirements planning consists of
        five steps as follows:

             1. Defining the resources to be considered
             2. Computing a load profile for each product that indicates what load is imposed
                on what resources by a single unit of the product
             3. Extending these profiles by the quantities called for by a proposed MPS and
                thus determining the total load, or resource requirement, on each of the
                resources in question
   244   245   246   247   248   249   250   251   252   253   254