Page 250 - Orlicky's Material Requirements Planning
P. 250

CHAPTER 12   Master Production Schedule                                         229


             4. Simulating the effect of alternative MPSs
             5. Selecting a realistic schedule that makes the best use of (existing or planned)
                resources
             Defining the resources to be considered is a management function. Resources range
        from engineering personnel to cash to capital equipment and plant square footage. In the
        discussion that follows, only one such resource, productive capacity, will be referenced. For
        purposes of resource requirements planning, productive capacity may be subdivided
        into individual capacity resources or groups. For example, the entire machine shop may
        be defined as a resource, and the impact of a given MPS then is measured in terms of total
        load on the shop. Or the shop may be defined as two or more resources by function, such
        as heavy casting machining, miscellaneous machining, and sheet-metal operations.
        Individual departments or groups of departments may constitute measured resources. A
        still finer breakdown would identify work centers or even individual machines. A single
        critical machine legitimately may be identified as a resource under this approach.
             Resource requirements planning, however, is intended for relatively large group-
        ings because its purpose is not to determine the exact load on an individual resource but
        rather to evaluate the overall impact of a given MPS. Resource requirements planning is
        conducted on a macro level using rough approximations of load, and a precise fit is not
        sought. The important thing is to be able to develop the alternative loads quickly so that
        several different MPSs may be tried out.
             Computing load profiles for individual products is based on the simple proposition
        that each (quantity of) product in the MPS generates measurable load and that the same
        procedures that are used to arrive at a machine load report can be used to compute a
        product load profile. A given load profile consists, for instance, of the standard hours of
        fabrication required, by period, to produce one unit of product measured against what-
        ever fabrication resource is selected.
             The load profile for a given product may be thought of as a load report for a simu-
        lated product lot of one computed on a relative time scale. In Figure 12-2, the end of peri-
           FIGURE 12-2
                                             Product X
           A product load              Resource: Heavy Presses
           profile for a single
                                Standard Hours
           resource.










                                    1    2    3    4   5    6    7    8    9   10
                                                       Periods
                                                                              Product Lot
                                                                               Due Date
   245   246   247   248   249   250   251   252   253   254   255