Page 275 - Orlicky's Material Requirements Planning
P. 275

254                                                 PART 3      Managing with the MRP System


             The instrument of priority control is a dispatch list or departmental schedule, typi-
        cally generated daily or weekly (the latter is of lower effectiveness), that may be in the
        form of a printed report, cards, or individual work-sequence messages or conveyed
        through a visual-display device. In any of these cases, the essence of the dispatch list is a
        ranking, by relative priority, of jobs (material that an operation is to be performed on)
        physically present in a manufacturing department and sometimes of jobs about to arrive
        in the department. A sample dispatch list is shown in Figure 13-2.
             The sequence of work established by the dispatch list is based on operation priori-
        ties, which, in turn, are derived from order priorities.  As order due dates are being
        revised via the MRP system, operation priorities must be reestablished accordingly. They
        may be expressed by means of operation start dates (as in the Figure 13-2 example) or
        operation finish dates, and if so, the affected orders first must be rescheduled by the oper-
        ations scheduling system. Alternatively, the priorities can be expressed by means of one
        of a variety of priority ratios that are geared to order due dates.
             A priority control system (i.e., dispatching or job sequencing) and its related instru-
        ments exist in every manufacturing plant in some form. Without input from an MRP sys-
        tem, however, a priority control system cannot function very effectively because the
        information tends to be out of date, invalid, and untrue. Shop personnel do not and can-
        not rely on this information, and so the system must be supplemented by expediting of
        shortage lists. The shortage lists, incomplete as they usually are, then reflect the true pri-
        orities.

           FIGURE 13-2
           Daily dispatch list.


                                            Dispatch List
                            Department: No. 12 Turret lathes         Date: March 15
                    Jobs in department
                    Order #  Part #  Quantity  Operation #  Start Date  Std. Hours  Remarks
                    5987  B-3344    50      30        3/7      3.2    Tooling in repair
                    5968  B-4567   100      25       3/12      6.6    Eng. hold
                    5988  F-8978    30      42       3/14      4.8
                    5696  12-1133  300      20       3/15     14.5
                    5866  A-4675    60      20       3/15      7.0
                    5996  A-9845   200      30       3/16      6.2
                    5876  F-4089    25      40       4/10      5.4

                    Jobs scheduled to arrive this date
                    6078  A-3855   160      30       3/14      6.5    In dept. 15
                    6001  D-8000   300      65       3/16      9.8    In dept. 08
   270   271   272   273   274   275   276   277   278   279   280