Page 277 - Orlicky's Material Requirements Planning
P. 277

256                                                 PART 3      Managing with the MRP System


           FIGURE 13-3                       Current
                                             Period
           Typical load        Behind
           pattern.            Schedule




                                                                           Capacity



















             This pattern still can be found in the load reports of many manufacturing compa-
        nies and plants. The manager evaluating the information understands that shop orders
        released in the current (first) period will add their load to the second period and those
        beyond, orders released in the next period will add their load to the third period and
        those beyond, and so on. He or she can only estimate, or guess, what the total load in any
        of the future periods will turn out to be. But this would seem to be less important than
        the question of when the behind-schedule load will be worked off. It assuredly will not
        happen in the current period, which is already overloaded. The manager knows, from
        experience, that next period’s load report likely will indicate an overload in the second
        period, which then will be current. He or she also knows that a relatively heavy behind-
        schedule load appears to be a permanent condition, according to the load report. This
        work center may be the bottleneck or constraint for the entire plant if this is indeed the
        permanent condition.
             The manager who tries to work with this type of load report may be baffled by the
        curious fact that while the load report always has indicated a highly unsatisfactory capac-
        ity situation relative to current and behind-schedule work load, shipments of the prod-
        uct have been more or less on schedule. Accordingly, he or she views the load data with
        healthy skepticism and is loath to act on the information provided by the load report. The
        load pattern illustrated in Figure 13-3 constitutes virtual proof that the load report
        exhibiting it is
             1. Incomplete because it fails to include load that will be generated by planned
                orders
             2. Invalid because priorities are not being kept up to date
   272   273   274   275   276   277   278   279   280   281   282