Page 281 - Orlicky's Material Requirements Planning
P. 281

260                                                 PART 3      Managing with the MRP System


             2. Priorities:
                ■ Order with the right due date.
                ■ Keep the due date valid.
             3. Capacity:
                ■ Determine a complete load.
                ■ Determine an accurate (valid) load.
                ■ Allow an adequate time span for visibility of future load.

             A full and proper use of the MRP system, represented by the preceding checklist,
        will prove difficult or impossible unless the system’s design anticipates such use. The
        intended use of the system therefore should dictate a number of critical design decisions,
        in particular:
             1. The span of the planning horizon
             2. The size of the time bucket
             3. The coverage of inventory by class
             4. The frequency of replanning
             5. The traceability of requirements
             6. The capability to “freeze” planned orders


                                  Planning-Horizon Span

        For purposes of inventory ordering, the planning horizon should at least equal the
        (longest) cumulative product lead time, as defined in Chapter 7. If the horizon is shorter
        than this, the MRP system will be unable to time releases of planned orders for items at
        the lowest level correctly, with the result that orders for such items (e.g., purchased mate-
        rials and component parts) will be consistently released too late. The system, in succes-
        sively offsetting for lead time in the course of the level-by-level planning process, simply
        runs out of available time when it reaches the items on the lowest level. This is due to a
        lack of information input to the system rather than a computing constraint.
             This is illustrated in Figure 14-1, where the cumulative lead time is 15 periods and
        the planning horizon is 13 periods. The order for purchased material, developed by the
        system through explosion of an end item inserted into the master production schedule
        (MPS) at the very edge of the planning horizon, should have been released two periods
        ago, based on the lead-time values supplied to the system. The best the system can do,
        under these circumstances, is to plan the order release for the current period. The order
        then is two periods behind schedule before it is even released.
             Because of the multilevel product structure and successive lead-time offsetting,
        there is a partial loss of horizon at lower levels. The effective planning horizon is succes-
        sively diminished as the planning process progresses from one level to the next. The
        lower the level, the less visibility there is into the future. For example, in Figure 14-1, a
        planned-order release for the fabricated item never can be farther out than period 3. The
   276   277   278   279   280   281   282   283   284   285   286