Page 191 - Pipeline Pigging Technology
P. 191

Pipeline  Pigging  Technology


     mechanical  pigs,  and  degreaser  were  then  launched  (injected)  into  the
     pipeline, in the appropriate sequence  (see  Fig.3).
        The  pig  train  was  driven  with  compressed  air  at  a  target  velocity of
     approximately  2ft/sec,  which  is considered  to  be  the  optimum speed  for
     debris removal with the gellypig. On the average, gellypig trains are generally
     driven between  l-3ft/sec,  dependent  upon  the  parameters of the  specific
     situation.  Missouri  Pipeline personnel  (or  its  contractors),  monitored  the
     progress of the trains. The velocities of both trains were very good, with Phase
      2 being relatively low, due  to intentionally stopping  the  train at times, for
     various reasons. The maximum pressure required to push the gellypig trains
     was approximately 220-230psig, with the pressures generally ranging from
      180-200psig.
        When the pig train arrived at the end of each section, the mechanical pigs
     were retrieved, and the gellypigs and degreaser diverted into frac. tanks. The
     separator gel is a cross-linked polymer, which creates a very viscous three-
     dimensional  gel. As the  separator  gellypig was  directed  towards  the  frac.
     tanks, a "breaker" was added to the gel, to "break" the cross-linked chemical
     bonds,  thereby  reducing  the  viscosity of  the  gel.  Samples of  the  gel  and
     degreaser were taken from the various sections of the pig train for laboratory
     analysis.
        All gellypigs, degreaser,  and material removed from  the  pipeline,  were
     stored in 21,000gall holding tanks (frac. tanks), at Chantilly and Curryville. DS
     arranged  for  disposal,  and  assisted  in  characterizing  the  waste.  Missouri
     Pipeline  provided  an  EPA generator  number  and  manifested  the  waste.
     Samples of the waste were obtained from each tank, and the waste character-
     ized. A reputable, licensed disposal firm was then contracted to dispose of the
     material in accordance  with  any and  all applicable  local, state,  and  federal
     rules and regulations. The gellypigs are non-regulated, non-hazardous, biode-
     gradable  materials, and  present  no  environmental  problems  in  disposal.
     However, due to the changing composition of the gel as it passes through the
     pipeline, precautions must be taken to properly dispose of the used gels and
     materials.
        The  pipeline  was  successfully  hydrotested  after  the  gellypig  service.
     Drying of the pipeline was accomplished  by Missouri Pipeline using metha-
     nol, mechanical (cup)  pigs, and many foam  swab pigs.
        Overall, the  execution  of the job went very well and according to plan,
     although  there  were  some  minor complications,  primarily caused  by  the
     extremely  cold weather.  Temperatures plunged to below  0°F, and around
     -50°F wind chill factor, during some portions of the job. This presented  some
     minor freezing  problems when  mixing the gels, storing the waste materials
     until they could be transported,  cleaning the frac. tanks, and some mechani-



                                       172
   186   187   188   189   190   191   192   193   194   195   196