Page 328 - Pipeline Pigging Technology
P. 328

Assessment of pipeline  dejects








































            Fig.5. Obtaining corrosion rate from repeat inspections.
         The following procedure  is suggested for determining the most severely-
      corroded  spools  and  corrosion  rates  from  the  results  of  repeat  on-line
      inspection.

         Quantifying corrosion         rates and severely-corroded
            spools



         Single  inspection

         The results from  a single  inspection  run  are  easily evaluated,  as spools
      exhibiting the highest maximum and mean metal loss readings can be readily
      identified. Prior to a second inspection, spools with 'high' maximum or mean