        Materials

        Any materials or components, whether new or used, that are added to the
      existing system have to meet certain requirements. This includes both  the
      selection  and qualification.


        Design

        Pipe - this covers internal and external pressures and loads.
        Components - involve all valves, fittings, fabricated assemblies, etc., that
      are subject to the system pressure.

         Welding

        Any  welding  done  on  a  pipeline  has  to  meet  the  applicable  welding
      requirements. This includes the welding of clamps and  sleeves.

         Construction


        Construction regulations cover a broad range of activities. The regulations
      are directed  to new construction, but also pipe replacement and relocation
      that is part of rehabilitation  work.  Also, anything that applies  to a new  line
     would certainly be a valid guideline for the rehabilitation of a line.
        Some  key  areas  are  inspection  of  materials and  work,  repair  of  pipe,
      installation of pipe in the ditch, backfill  and cover  over the buried pipeline.
      In addition, various construction  and as-built records  are  required.

         Testing  requirements

        This is an area that certainly requires careful  consideration.  The general
      requirement  sections  for testing  under both  the  natural-gas and hazardous-
      liquid  regulations  have  not  been  definitively interpreted.  In  the  case  of
      Method 2, there would be no question as to the requirements for hydrostatic
      testing under the requirements  of either  the gas or liquid regulations. Also,
     with increased emphasis on protecting  the environment, the handling of the
      test water is very crucial.