Page 115 - Pipeline Rules of Thumb Handbook
P. 115

102     Pipeline Rules of Thumb Handbook

         Complete tables giving capacities of different types of tubular  L t = L o (1 + .0000069t)
         goods are given in chapters dealing with these types.
                                                               where L o = Length at atmospheric temperature
                                                                     L t = Length after change of temperature t
         Steel constants* (applicable to tubular goods)
                                                                                       p
                                                               Modulus: Section Modulus  ( D - D 1 )
                                                                                                4
                                                                                           4
         One cubic inch = 0.2833lb                                                     64
         One cubic foot = 489.542lb                                     Polar Modulus  (  4   1 )
                                                                                     p
                                                                                               4
         Specific gravity = 7.851                                                     32  D - D
         Approximate coefficient of expansion for commercial casing,  where D = Outside diameter
         drill pipe, and tubing is                                   D 1 = Inside diameter
                                                                      p = 3.1416
                            -6
         Coefficient = 6.9 ¥ 10 per °F, over range from 0 to 400°F
                                                               Relation between twisting effort, torsional strain and stress of
         Formula for expansion of pipe due to change of temperature
                                                               cylindrical shaft or tube
         is as follows:
                                                                q  T   Cq
                                                                 =   =
         * Engineering data Spang-Chalfant Division of the National Supply Co.  r  J  L
         How to calculate the contraction or expansion of a pipeline


           Steel pipe contracts or expands approximately 0.8 inch per     = 0 8 10 1
                                                                            .
                                                                                  ¥
                                                                              ¥
         100°F temperature change for each 100 feet of pipe. For con-     = 8 inches
         struction in the U.S., slack is not normally needed in welded
         lines for contraction or expansion unless abnormal variations  Large temperature changes may arise on exposed line or in
         are encountered. However, slack is often provided near road  lines downstream from compressor stations.
         crossings where the pipe may have to be lowered at some  When slack is desired in a line, the amount of sag or rise
         future time.                                          needed may be estimated quickly. To provide for 0.8 inch of
                                                               movement longitudinally along the pipe, a sag of 21 inches
                                                               would be needed in a 100-foot loop. For a 150-foot loop, 31
                       .
          Contraction = 08  ¥                                  inches are necessary. Such slack put into the line at time of
                                  (
                      length of pipe feet)  temp change ∞ (  F)  construction might allow for lowering the pipe under road-
                                             .
                                       ¥
                             100               100             beds without putting excessive stress upon the pipe.
                                                                 Location of overbends, sags, and side bends should be con-
                                                               sidered when laying slack loops. When loops are placed, parts
           Example. Calculate the amount a 1,000-foot section of
                                                               of the line should be backfilled to serve as a tie-down. Loops
         pipeline would contract if laid at a temperature of 100°F and
                                                               should be lowered during the coolest part of the day when
         cooled to a low of 0°F during winter operation. (Assuming
                                                               the line is the shortest. After lowering in, sags should rest on
         the line were free of soil or other resisting loads.)
                                                               the bottom of the ditch; overbends should “ride high.” Side
                                                               bends should rest on the bottom of the ditch and against the
                          1 000  100                           outside wall. The line should be lowered so that all sections
                           ,
                      .
          Contraction = 08  ¥  ¥
                           100   100                           of the pipe are in compression.
         Estimate weight of pipe in metric tons per kilometer

           To estimate the weight of pipe in metric tons per kilo-  Actual answer from pipe tables is 79 metric tons per
         meter, multiply the nominal diameter by the number of six-  kilometer.
         teenths of an inch in wall thickness.                   This rule of thumb is based on a density of 490 pounds per
                                                               cubic foot for steel. For larger diameter thin wall pipe, this
           Example. Find the weight of pipe in metric tons per kilo-  approximation gives an answer usually about one percent low.
                                                  1
         meter for 20-inch diameter pipe, wall thickness  / 4 -inch.  The accompanying table gives a comparison between actual
                                                               weights in metric tons per kilometer, as compared to that
                             )
          4 ¥  20 =  80 tons  (metric per kilometer            calculated by this rule of thumb.
   110   111   112   113   114   115   116   117   118   119   120