Page 51 - Pipeline Rules of Thumb Handbook
P. 51

38    Pipeline Rules of Thumb Handbook

         Clearing and grading right-of-way


                           Equipment Spread                                         Labor Crew

                              NUMBER OF UNITS FOR                                    NUMBER OF MEN FOR

                     50 Linear Feet  80 Linear Feet  100 Linear Feet       50 Linear Feet  80 Linear Feet  100 Linear Feet
                        Width         Width         Width                     Width        Width          Width
         Equipment                                             Personnel
         Description  L  M  MH  H  L  M  MH  H  L  M  MH  H    Description  L  M  MH  H  L  M  MH  H  L  M  MH  H

         D8 Tractor                                            Foreman .....  1  1  2  2  1  2  3  3  2   3  4   4
           W/Dozer ... 1  1  1  1  1  1  2   2  1  2   3   3   Operator .....  1  1  2  2  1  2  3  3  2  4  5   5
         D7 Tractor                                            Mechanic ....  1  1  1  1  1  1  1  1  1   1  1   1
           W/Dozer ... 0  0  1  1  1  1  1   1  1  1   2   2   Swamper ....  1  1  2  2  1  2  3   3  2   4  5   5
                1
         Truck—2 / 2                                           Truck Driver  2  2  2  2  2  2  2   2  2   2  3   3
           Ton Dump  2  2  2   2  2  2   2   2  2  2   3   3   Laborer ....... 10 15  20  30 15 25  30  40 20 35  40  50
         Truck—                                                Total Crew .. 16 21  29  39 21 34  42  52 29 49  58  68
           Pick-up ..... 1  1  2  2  1  2  3  3  2  3  4   4
         Ripper or
           Brushrake  1  1  1  1  1  1   1   1  1  2   2   2

           Above equipment spread should be ample for clearing and  Above total crew should be ample for clearing and grading
         grading one mile of right-of-way per 10-hour day for the  one mile of right-of-way per 10-hour day for the width and
         width and conditions as are outlined. Haul trucks are based  conditions outlined. Crew spread includes cutting, stacking or
         on round trip haul of two miles. If brush and trees are to be  piling, loading, and hauling a round-trip distance of two miles.
         burned on site, omit above dump trucks. Small tools such as  If burning is necessary or permitted, substitute fire tenders
         saws, axes, etc., must be added as required for the individual  for dump truck drivers. See Clearing and Grading equipment
         job.                                                  spread for number of dump trucks.

           Code description.                                     Code description.

           L = Light—light brush and grass, no trees.            L = Light—light brush and grass, no trees.
           M = Medium—considerable brush of larger size.         M = Medium—considerable brush of larger size.
         MH = Medium Heavy—large brush and small trees.        MH = Medium Heavy—large brush and small trees.
           H = Heavy—much small brush, many small trees, and     H = Heavy—much small brush, many small trees, and
               occasional large trees.                               occasional large trees.



                                                                                     Source

                                                               Page, J. S., Cost Estimating Man-Hour Manual for Pipelines
                                                                 and Marine Structures, Gulf Publishing Co., Houston,
                                                                 Texas, 1977.
   46   47   48   49   50   51   52   53   54   55   56