Construction  37

             10. Grading irregularities where required.            13. Protecting and preserving existing drainage facilities.
             11. Preserving topsoil for replacement, through all culti-  14. Protecting any existing structures or pipelines.
                vated or improved fields and pastures, to its original  15. Protecting any telephone or utility lines and keeping
                position.                                             them in service.
             12. Proper grading of the terrain so as to allow passage of  16. Cutting through fences and hedges where required
                loaded trucks and equipment hauling materials and so  and replacing these when necessary.
                ditching operations can be properly performed.     17. Installing gates and fences where required.



           Estimating manhours for removing trees


                         NET MANHOURS—EACH

                           Softwood Trees     Hardwood Trees                     Softwood Trees     Hardwood Trees
           Average Tree                                          Average Tree
           Diameter       Open   Congested   Open   Congested    Diameter       Open   Congested   Open   Congested
           in Inches      Area     Area      Area     Area       in Inches      Area     Area      Area     Area
           Cross-cut Saws                                        Chain Saws
           4               1.49     1.86      1.88     2.35      4               0.37     0.46      0.47     0.59
           6               2.26     2.83      2.82     3.53      6               0.57     0.71      0.71     0.89
           8               3.24     4.02      4.00     4.96      8               0.81     1.00      1.00     1.24
           10              4.10     5.08      5.00     6.20      10              1.03     1.28      1.25     1.55
           12              4.98     6.18      6.00     7.44      12              1.25     1.55      1.50     1.86
           14              6.39     7.86      7.70     9.47      14              1.60     1.97      1.93     2.37
           16              7.39     9.09      8.80    10.82      16              1.85     2.28      2.20     2.71
           18              8.32    10.23      9.90    12.18      18              2.08     2.56      2.48     3.05
           20             10.58    12.91     12.60    15.37      20              2.65     3.23      3.15     3.84
           24             12.71    15.51     15.12    18.45      24              3.18     3.88      3.78     4.61
           30             17.09    20.85     20.10    24.52      30              4.28     5.22      5.03     6.14
           36             20.50    25.01     24.12    29.43      36              5.13     6.26      6.03     7.36

             Manhours include ax trimming, cutting down with cross-  Manhours do not include hauling, piling and burning of
           cut saws or chain saws, and cutting into four-feet lengths for  trees or branches, or the removal of stumps.
           the tree diameter sizes as listed above. Manhours are average
           for various heights of trees.




           Estimating manhours for removing tree stumps


                         NET MANHOURS—EACH                                     NET MANHOURS—EACH
                                          Oper. Powder                                          Oper. Powder
           Item                  Laborer  Engr.   Man    Total   Item                  Laborer  Engr.   Man    Total

           Grub & Removal by Hand                                Blast & Pull with Tractor
           8≤ to 12≤ diameter      6.00    —       —     6.00    8≤ to 12≤ diameter       .83    .11    1.50   2.44
           14≤ to 18≤ diameter     7.50    —       —     7.50    14≤ to 18≤ diameter     1.05    .23    2.33   3.61
           20≤ to 24≤ diameter     9.00    —       —     9.00    20≤ to 24≤ diameter     1.50    .30    3.38   5.18
           26≤ to 36≤ diameter     11.20   —       —     11.20   26≤ to 36≤ diameter     2.11    .42    4.76   7.29

             Manhours include excavating and removing by hand or
           blasting and removing with cables and tractors. Manhours do
           not include burning or removal from premises.