Page 280 - Pipelines and Risers
P. 280

Remaining Strength of Corroded Pipes                                  253

















         Figure 14.12 Expected Corrosion Depth Over Time for Different Inhibitors.

                                c       I  I  I   I  I  I   I  I  I
                                5












         Figure 14.13 Annual Failure Probability for Different Inhibitors.

         Evaluation of Alternatives
         The selection of  the minor repair/modification alternatives (de-rating or inhibitors) satisfies
         the constraints. Table 14.3 summarizes the combination effects. It summarizes the operating
         time after 10 years service until the target probability   is reached.


         If the next inspection is not scheduled prior to 15 years of  service, the combinations of de-
         rating and inhibitors in the shaded area of  Table 14.3 are the realistic decision alternatives.
         The darker shaded area indicates the most  attractive combination of  use of  inhibitor with
         specified effect and degree of pressure reduction. If  the pipeline inspection is rescheduled, the
         alternatives of upper left comer in Table 14.3 are recommended. However, in the evaluation
         of  the  alternatives incorporating a reduction  of  the time  period  until  next  inspection, the
         likelihood of possible major repaidmitigate measures at an earlier period should be addressed
         in the decision process.