Page 143 - Practical Power System and Protective Relays Commissioning
P. 143
142 Practical Power System and Protective Relays Commissioning
FIGURE 13.1 Fault recorder unit setup.
13.2 FAULT RECORDER TESTING
These tests include the following:
1. Adjusting the prefault, fault, and postfault times on the fault recorder
units and check that they are working correctly for a simulated fault by
secondary injection. Check the operation of both the analog channels and
the digital channels.
2. Check that all points of analog channels and digital channels are trans-
ferred to the local and remote annunciator inside the substation.
3. Check that all points of analog channels and digital channels are trans-
ferred to the National Control Center SCADA system.