142  Practical Power System and Protective Relays Commissioning
























            FIGURE 13.1 Fault recorder unit setup.

            13.2 FAULT RECORDER TESTING

            These tests include the following:
            1. Adjusting the prefault, fault, and postfault times on the fault recorder
               units and check that they are working correctly for a simulated fault by
               secondary injection. Check the operation of both the analog channels and
               the digital channels.
            2. Check that all points of analog channels and digital channels are trans-
               ferred to the local and remote annunciator inside the substation.
            3. Check that all points of analog channels and digital channels are trans-
               ferred to the National Control Center SCADA system.