Page 353 - Practical Well Planning and Drilling Manual
P. 353

Section 3 revised 11/00/bc  1/17/01  12:00 PM  Page 329








                                                                                  3.1.8
                                                                     Well Control  [     ]



                           The complete BOP system should be tested at the following intervals:

                           After installation of the wellhead and BOP prior to drilling
                           After 7 days, which may be extended to 14 days depending on the
                           operations in progress and pending
                           Prior to drilling into expected hydrocarbon reservoirs or overpres-
                           sured formations
                           Prior to a production test
                           At any time if any doubt arises over the stack integrity, such as
                           after repairs


                           The accumulator should be tested at the same time as the BOP
                       stack. They can be done together by switching off the accumulator
                       charge pumps and using the stored energy to operate the BOPs while
                       carrying out the pressure test. In addition, the accumulator should be
                       tested after repairs have been made to the system, such as bottles, blad-
                       ders, pumps, etc.
                           The accumulator bottles precharge pressure shall be checked prior
                       to drilling out cement in the casing shoe. Unless otherwise specified
                       the precharge pressure for a 3000 psi system shall be 1000 psi.
                           After nippling up, the wellhead and BOPs should be subjected to a
                       500 psi pressure test followed by a high-pressure test to the lower of
                       rated BOP or wellhead/casing pressure. Subsequent pressure tests are to
                       the maximum anticipated wellhead pressure, with a maximum on the
                       annulars of 70% of working pressure. Kill and choke lines and mani-
                       folds are tested to the lesser of ram or manifold working pressure, but
                       no tests shall be made against closed chokes. Kelly/TDS and kelly cocks
                       are tested to their rated pressure. Test pressures in each case are to be
                       held for at least 10 minutes; this implies that if the pressure drops ini-
                       tially then settles down (air in system), then it can be repressured and
                       held. However, a steady drop indicates a leak that must be investigated
                       and fixed.
                           The suggested BOP test procedure below shows a suggested
                       method of testing a 3-ram surface stack, where the test pressures are
                       the same as the casing test pressure. Kill and choke manifolds, kelly
                       and stab-in valves may be tested during tripping or other operations to
                       save time, so long as the normal shut-in procedure can be used in the
                       event of a trip drill or kick.


                                                     329
   348   349   350   351   352   353   354   355   356   357   358