Page 184 - Shale Shakers Drilling Fluid Systems
P. 184

DILUTION  167



        drilling fluid is needed to dilute the drilled solids  drilling fluid is also the removal efficiency that
        returned to the system, 286 bbl of drilling fluid is  generates the minimum discard volume.
        needed to maintain the pit levels, which will de-        These three calculations are summarized in Fig-
        crease the drilled solids concentration. In other     ure 8-4. The minimum volume required is the low-
        words, a 4% volume drilled solids level cannot be     est point on the curve at the 90% removal effi-
        sustained with constant pit volume and 100% re-       ciency point.
        moval efficiency.
           At 90% removal efficiency, 90 bbl of drilled
        solids and 167 bbl of drilling fluid are removed         OPTIMUM REMOVAL EFFICIENCIES
        from the system. In this case, the pit levels decrease
        by 257 bbl (Figure 8-2). The solids returned to the      The previous examples, with 35% volume sol-
        system (10 bbl) must be diluted to 4% volume con-     ids in the discard, illustrate that an optimum
        centration by adding 240 bbl of new drilling fluid.   removal efficiency of around 90% exists for the
        The total addition to the pit system is 10 bbl of     4% volume target concentration of drilled solids.
        drilled solids and 240 bbl of new drilling fluid. This  These same calculations may be made for other
        means that 7 bbl of new drilling fluid must be built  discard and targeted drilled solids concentrations
        to maintain the pit levels.                           as illustrated in Figure 8-5.
           This example illustrates a system that is almost      For example, if the removal efficiency is 75%,
        "balanced." If the discarded volume is identical to   over 6 bbls of drilling fluid is required for each
        the volume required for dilution, the minimum         barrel of drilled solids reporting to the surface
        quantity of drilling fluid will be built. The optimum  when the targeted drilled solids concentration is
        removal efficiency for any targeted drilled solids level  4% by volume.
        may be calculated by mathematically equating the         Using the same calculation procedures for 6%
        removal volume to the required dilution volume.       volume targeted drilled solids, Figure 8-5 shows
           In the case of 80% removal efficiency, 229 bbl     that at 60% removal efficiency, over 6.2 bbls of
        of drilled solids and drilling fluid will be dis-     drilling fluid will be required for every barrel of
        charged (Figure 8-3). Although this is only 21 bbl    drilled solids reaching the surface. As the effi-
        less than the 90% removal efficiency, the dilution    ciency improves, the drilling fluid requirement
        volumes are significantly higher. The dilution of     decreases: at 70% slightly more than 4.5 bbl is
        the 20 bbl of returned drilled solids to a 4% vol-    required per barrel of solids; at 80% slightly more
        ume level requires the addition of 480 bbl of         than 3 bbl is required; and at 85% almost 2.5 bbl
        new drilling fluid to the system. The reconstituted   is required. For removal efficiencies greater than
        500 bbl of drilling fluid will contain 20 bbl of      85%, the pit level decreases more than the addi-
        drilled solids and 480 bbl of clean drilling fluid.   tional new fluid required to dilute the solids to the
        Since only 229 bbl of space is available, 271 bbl of  6% volume level. This additional fluid will dilute
        fluid must b^ discarded to keep the pit levels con-   the solids to a value lower than 6% volume.
        stant. Therefore, the total discard is the 229 bbl       The volume of drilling fluid required per barrel
        from the solids-removal equipment plus 271 bbl of     of drilled solids is similar whether the slurry is wet
        drilling fluid.                                       (25% volume solids) or relatively dry (45% volume
           This situation creates a problem: if 271 bbl of    solids). When the removal efficiency is below the
        drilling fluid is not discarded, the drilled solids   "balance point," the values are identical. As the
        concentration will increase significantly above the   concentration of drilled solids decreases, the bal-
        targeted 4% volume concentration. When large          ance point for any target concentration of drilled
        reserve pits were used, drilling fluids were rela-    solids increases. The volume of new drilling fluid
        tively inexpensive and disposal costs were insig-     required above the balance point is independent
        nificant. Building excess volume was more of an       of the dryness of the discarded solids.
        inconvenience than a significant economic burden.
        If drilling fluid disposal volumes are to be main-
        tained as low as possible (i.e., no drilling fluid     DETERMINING REMOVAL EFFICIENCIES
        jetted from the pits), the removal efficiency must
        be improved. Otherwise the 4% volume of drilled         If a well is spudded with fresh water and the
        solids will not be attained.                          pit levels remain constant during drilling, the drilled
           The minimum discard volume will occur when         solids returned to the system will increase the
        the system is "balanced" (i.e., no excess drilling    density. This analysis assumes that no whole drill-
        fluid is needed to dilute the drilled solids return-  ing fluid is emptied from the system or lost down-
        ing to the system). The same solids removal effi-     hole. As the borehole becomes deeper, the mud
        ciency that provides the minimum quantity of new      weight increases at different rates for different re-
   179   180   181   182   183   184   185   186   187   188   189