Page 118 -
P. 118

6 - PROJECT TIME MANAGEMENT






                   6.5.3.2 Project Documents Updates


                      See Section 6.5.3.2 of the PMBOK  Guide.
                                                   ®

                   6.6 Develop Schedule


                      The form of a software project schedule may be the same as described in Section 6.5 of the PMBOK  Guide or
                                                                                                           ®
                   it may take a different form altogether. In addition to the approach described in the PMBOK  Guide, a more flexible
                                                                                               ®
                   approach facilitates the expected changes that inevitably occur in a software project schedule. Software project
                   schedules and plans change, driven by customer requests, project feedback, and by the emergence of previously
                   unidentified work activities. The form of software project schedule used may be unfamiliar to some stakeholders.
                   For example, a prioritized backlog of work may be the preferred method for illustrating and managing the sequence
                   of project activities instead of a network diagram. The approach of maintaining a prioritized backlog of work
                   activities is similar to rolling wave planning, where a top-level schedule is maintained for the entire project and only
                   the proximate elements of the schedule are completed in detail as the project evolves.



                   6.6.1 Develop Schedule: Inputs

                      The inputs for developing a project schedule in the PMBOK  Guide are applicable inputs for developing a
                                                                          ®
                   software project schedule. Additional inputs are described in Section 6.6.1.14.


                   6.6.1.1 Schedule Management Plan


                                                   ®
                      See Section 6.6.1.1 of the PMBOK  Guide.

                   6.6.1.2 Activity List

                                                   ®
                      See Section 6.6.1.2 of the PMBOK  Guide.

                   6.6.1.3 Activity Attributes

                      See Section 6.6.1.3 of the PMBOK  Guide.
                                                   ®


                   6.6.1.4 Project Schedule Network Diagrams

                      See Section 6.6.1.4 of the PMBOK  Guide.
                                                   ®











          108      ©2013 Project Management Institute. Software Extension to the PMBOK  Guide Fifth Edition
                                                                   ®
   113   114   115   116   117   118   119   120   121   122   123