6 - PROJECT TIME MANAGEMENT






                   6.7.1 Control Schedule: Inputs


                      The inputs for controlling a project schedule in Section 6.7.1 of the PMBOK  Guide are applicable inputs for
                                                                                       ®
                   controlling software project schedules, with the modification of 6.7.1.3 below.


                   6.7.1.1 Project Management Plan

                      See Section 6.7.1.1 of the PMBOK  Guide.
                                                   ®

                   6.7.1.2 Project Schedule                                                                               6

                      See Section 6.7.1.2 of the PMBOK  Guide.
                                                   ®


                   6.7.1.3 Work Performance Data

                      The cadence of recent work completed, current velocity metrics, and service-level agreements for on-demand
                   scheduling can provide inputs for controlling the schedule of an adaptive life cycle software project.


                   6.7.1.4 Project Calendars

                      See Section 6.7.1.4 of the PMBOK  Guide.
                                                   ®

                   6.7.1.5 Schedule Data


                                                   ®
                      See Section 6.7.1.5 of the PMBOK  Guide.

                   6.7.1.6 Organizational Process Assets

                                                   ®
                      See Section 6.7.1.6 of the PMBOK  Guide.

                   6.7.2 Control Schedule: Tools and Techniques

                      The tools and techniques presented in Section 6.7.2 of the PMBOK  Guide for controlling a project schedule
                                                                                ®
                   are applicable to controlling the schedule of a software project with the indicated modifications and the addition
                   of 6.7.2.9 through 6.7.2.14 (below).


                   6.7.2.1 Performance Reviews

                      In many software projects, performance reviews, as described Section 6.7.2.1 of the PMBOK  Guide, are part of
                                                                                                   ®
                   the technical review cycle. In most cases, the best measurement of performance is the value created/delivered over