8 - PROJECT QUALITY MANAGEMENT
8.3.1 Control Quality: Inputs
The inputs for controlling quality in Section 8.3.1 of the PMBOK Guide are applicable inputs for controlling quality
®
for software projects. As described in the PMBOK Guide, inputs to software quality control include management
®
plans and checklists. Another significant input is the measurement plan for the prioritized quality attributes as
defined in the release criteria. Project records, especially testing and configuration management records, are
essential inputs and are typically maintained in controlled repositories.
8.3.1.1 Project Management Plan
See Section 8.3.1.1 of the PMBOK Guide.
®
8.3.1.2 Quality Metrics
See Section 8.3.1.2 of the PMBOK Guide.
®
8.3.1.3 Quality Checklists
See Section 8.3.1.3 of the PMBOK Guide.
®
8.3.1.4 Work Performance Data
®
See Section 8.3.1.4 of the PMBOK Guide.
8.3.1.5 Approved Change Requests
See Section 8.3.1.5 of the PMBOK Guide.
®
8.3.1.6 Deliverables
®
See Section 8.3.1.6 of the PMBOK Guide.
8.3.1.7 Project Documents
See Section 8.3.1.7 of the PMBOK Guide.
®
8.3.1.8 Organizational Process Assets
See Section 8.3.1.8 of the PMBOK Guide.
®